Provenance¶
This document was generated based on the contents of the lsst-dm/milestones repository, version 67eea9e1, dated 2021-02-04. This corresponds to the status recorded in the project controls system for December 2020.
Notation¶
Throughout this document, the identifiers of completed milestones are set in italics; those of milestones which are still pending, in roman.
Summary¶
The DM Subsystem is currently tracking 378 milestones: 7 at Level 1, 78 at Level 2, 280 at Level 3, and 8 at Level 4. 5 have no level defined. Of these, 297 have been completed. Of the incomplete milestones, 19 are late relative to the baseline schedule, while the remainder are scheduled for the future.
Currently overdue milestones¶
- DLP-526: Archive Center Integration Complete [Due 2021-01-28]
- LDM-503-11a: ComCam Ops Readiness [Due 2020-12-01]
- LDM-503-11b: Test report: Pipelines Release Fall 2019 [Due 2020-12-01]
- DM-AP-10: Advanced single frame measurement pipeline for Alert Production. [Due 2020-12-01]
- DM-DRP-13: PSF estimation over the full visit. [Due 2020-12-01]
- DM-DRP-22: Template generation integrated with Data Release Production pipelines. [Due 2020-12-01]
- DM-DRP-24: Physically motivated PSF model, including separate characterization of contributions from the atmosphere and the telescope system. [Due 2020-12-01]
- DM-DRP-29: Moving point source model fitting now available. [Due 2020-12-01]
- DM-DRP-37: Artifact rejection and background matching during coadd construction. [Due 2020-12-01]
- DM-DRP-8: Calibration product generation for the Auxiliary Telescope. [Due 2020-12-01]
- DM-SUIT-5: Search and display processed HSC data [Due 2020-12-01]
- DLP-802: Alert Production Database (APDB) design [Due 2020-12-01]
- DM-DAX-5: Database ingest in support of HSC reprocessing (ie, large catalog ingest) [Due 2020-12-01]
- DM-NCSA-21: L1 Offline Processing Service, Raft Scale, ComCam [Due 2020-12-01]
- DM-NCSA-23: Operational processes for preparing for & producing a data release defined and tested [Due 2020-12-01]
- DM-NCSA-8: Alert Filtering Service receives alert streams [Due 2020-12-01]
- IT-725-M: Base Data Center Network Complete [Due 2020-12-01]
- DLP-46: Full Capacity over Diverse path Ready [Due 2020-12-01]
- DMTC-8000-0990: Full capacity La Serena to Santiago over Primary link AND Secondary link - Complete [Due 2020-12-01]
Milestones by due date¶
Due in February 2023¶
- LDM-503-17: Final operations rehearsal
Due in January 2023¶
- LDM-503-16: Ops rehearsal for data release processing #3
Due in December 2022¶
- No milestones due.
Due in November 2022¶
- No milestones due.
Due in October 2022¶
- LDM-503-15: Ops rehearsal for data release processing #2
- LDM-503-17a: Test report: Final Pipelines Delivery
Due in August 2022¶
- No milestones due.
Due in July 2022¶
- DM-NCSA-24: Production batch service for data release processing
Due in June 2022¶
- DM-NCSA-26: Demonstrate full delivery of Data Facility ConOps
Due in May 2022¶
- No milestones due.
Due in April 2022¶
- No milestones due.
Due in March 2022¶
- F21F: F21 Complete
- LDM-503-12: Ops rehearsal for commissioning #3
- LDM-503-13: Ops rehearsal for data release processing #1 (ComCam data)
- LDM-503-14: Test report: DM Readiness for Science Verification
- LDM-503-12a: LSSTCam Ops Readiness
- DM-PORTAL: Resume development of LSP portal aspect
- DM-CLOUD: Decide on final data facility design for DR1
- LDM-503-EFDb: EFD/telemetry data replicated at the LDF, stored in InfluxDB. aggregated into parquet files
- LDM-503-EFDc: EFD data is queriable through TAP in the Science Platform
- DM-AP-14: Alert filtering system available.
- DM-DRP-20: Refined set of LSST calibration products.
- DM-SQRE-4: Notebook service ready for verification & validation
Due in February 2022¶
- No milestones due.
Due in January 2022¶
- No milestones due.
Due in December 2021¶
- S22S: S22 Start
- LDM-503-15a: Test report: Pipelines Release Fall 2021
- DM-AP-17: Moving object processing system (MOPS) available.
- DM-DRP-36: MOPS integrated to data release processing.
Due in November 2021¶
- DM-NCSA-14: Data Backbone endpoints in Chile for ingestion and access, distribution over WAN, ingest at NCSA into custodial file sto
- DM-NCSA-25: Demonstrate operational coordination with and processing at satellite CC-IN2P3 satellite computing facility
Due in October 2021¶
- LDM-503-EFDa: Engineering Facility Database at the summit capturing and enabling access to all telemetry with M1/M3 active
- DM-AP-16: Full integration of the Alert Production system within the operational environment.
Due in September 2021¶
- DMTC-8100-2450: FIU-CIARA Management Contract Delivery #7 Complete
Due in August 2021¶
- S21F: S21 Complete
- LDM-503-10b: Large Scale CCOB Data Access
- LDM-503-13a: Test report: Pipelines Release Fall 2020
- DM-DRP-23: Atmospheric characterization based on data from the Auxiliary Telescope now available.
- DM-DRP-31: A photometric redshift is now provided for each object.
- DM-DAX-13: Generation 2 middleware retired
Due in July 2021¶
- DM-NET-5: Base - Archive Network Functional 100 Gbps
- DLP-464: Install networking for normal Base Center operations for ComCam scale
- DLP-466: Install networking for ComCam-scale Chilean DAC serving on order 20 people
- DMTC-8200-6020: ESNet Implementation Phase 2- Complete
- F21S: F21 Start
- S21S: S21 Start
Due in June 2021¶
- DLP-465: Install networking for normal Base Center operations for full-camera scale
- DLP-468: Provide networking for formal Chilean DAC production at full-camera scale
- DLP-467: Install networking for full-camera-scale Chilean DAC serving on order 80 people
- DMTC-8100-2210: 100G ring operating at 99.99% availability - Complete
- DLP-877: Miami - Chicago Full Integration Ready
- DLP-876: Boca Raton - Chicago Full Integration Ready
- F20F: F20 Complete
- LDM-503-11: Ops rehearsal for commissioning #2
- LDM-503-14a: Science Platform ready for DP0
- DM-DRP-21: Integrated image characterization pipeline for Data Release Production.
- DM-DRP-30: Forced photometry is now performed on individual processed visit images during data releases.
- DM-DRP-25: Prototype multi-epoch fitting system available.
- DM-DRP-34: Selection maps are generated during data releases.
- DM-DAX-9: Provenance system
- DM-DAX-12: Generation 3 middleware at feature parity with Generation 2
- DM-DAX-14: Provenance system review completed
- DM-SQRE-6: IVOA Server-side Operations for Data Access API
- DM-SQRE-7: IVOA-compliant image metadata services
Due in May 2021¶
Due in April 2021¶
Due in February 2021¶
- DMTC-8100-2410: FIU-CIARA Management Contract Delivery #6 Complete
- DM-DRP-35: Simultaneous measurement across a suite of coadds representing different bandpasses, epocs, and flavors.
Due in December 2020¶
- DM-NCSA-8: Alert Filtering Service receives alert streams
- DM-NCSA-21: L1 Offline Processing Service, Raft Scale, ComCam
- DM-NCSA-23: Operational processes for preparing for & producing a data release defined and tested
- IT-725-M: Base Data Center Network Complete
- DLP-46: Full Capacity over Diverse path Ready
- DMTC-8000-0990: Full capacity La Serena to Santiago over Primary link AND Secondary link - Complete
- LDM-503-11b: Test report: Pipelines Release Fall 2019
- LDM-503-11a: ComCam Ops Readiness
- DM-SUIT-5: Search and display processed HSC data
- DM-AP-10: Advanced single frame measurement pipeline for Alert Production.
- DM-DRP-8: Calibration product generation for the Auxiliary Telescope.
- DM-DRP-13: PSF estimation over the full visit.
- DM-DRP-37: Artifact rejection and background matching during coadd construction.
- DM-DRP-22: Template generation integrated with Data Release Production pipelines.
- DM-DRP-24: Physically motivated PSF model, including separate characterization of contributions from the atmosphere and the telescope system.
- DM-DRP-29: Moving point source model fitting now available.
- DM-DAX-5: Database ingest in support of HSC reprocessing (ie, large catalog ingest)
- DLP-802: Alert Production Database (APDB) design
Due in November 2020¶
- DM-NCSA-15: Batch Processing Service for offline spectrograph data processing
- DM-NCSA-22: Information in consolidated database available to QA portal
- LDM-503-08: Test report: Spectrograph data acquisition
- LDM-503-09: Test report: Ops rehearsal for commissioning #1
- LDM-503-10: Test report: DAQ validation
- DM-DRP-12: Background estimation over the full visit.
- DM-DRP-15: All varieties of coadd required for object detection and characterization are now produced during normal pipeline operation (although not necessarily at the ultimately required level of fidelity).
- DM-DAX-7: Generation 3 Butler, running on a POSIX file-system provided by NCSA
- DM-DAX-8: Scatter-gather support in PipelineTask
Due in October 2020¶
- No milestones due.
Due in August 2020¶
- No milestones due.
Due in July 2020¶
- DMTC-8100-2170: 100G ring operating at 99.0% availability - Complete
Due in June 2020¶
- F20S: F20 Start
- LDM-503-06: Test report: DM ComCam interface verification readiness
Due in May 2020¶
- DLP-533: Base Center Integration Complete
- S20F: S20 Complete
- LDM-503-05: Test report: Alert distribution validation
- LDM-503-09a: Test report: Pipelines Release Fall 2018
- DM-AP-6: Alert format defined & queue system available.
- DM-AP-18: Alert packet generation
Due in April 2020¶
- No milestones due.
Due in March 2020¶
- No milestones due.
Due in February 2020¶
- DM-SQRE-3: Notebook service stable for commissioning and other internal project users
Due in November 2019¶
- F19F: F19 Complete
- DM-STAFF: Staffing Checkpoint
- LDM-503-08b: Small Scale CCOB Data Access
- DM-AP-11: Difference imaging includes noise decorrelation and correction for differential chromatic refraction.
Due in October 2019¶
- A1300: Start Milestone: October 1st, 2019
- DLP-70: Miami - Chicago Early Integration Ready
- DLP-69: Boca Raton - Chicago Early Integration Ready
- DMTC-8200-0600: ESNet Implementation Phase 1- Complete
Due in September 2019¶
- DM-NCSA-20: ComCam Archiving Service
- DMTC-8100-2370: FIU-CIARA Management Contract Delivery #5 Complete
Due in August 2019¶
Due in July 2019¶
- DM-NCSA-11: Verified acquisition of raw and crosstalk-corrected exposures at raft scale, incl. correct metadata
- A4369.9: Ship Hardware to BDC
- DM-NET-4: Base LAN installed
- LDM-503-10a: Science Platform: TAP service with federated SSO A&A
Due in June 2019¶
- A2330: Ship AA System to Chile
- A4640: Ship ComCam Hardware to Tucson
- DMTC-8000-0950: Technical Implementation Plan for 40Gbps diverse path - Complete
- F19S: F19 Start
Due in May 2019¶
- DM-NCSA-13: Header Writing Service for Spectrograph use case
- A5090: Expected Arrival of ComCam Systems to NCSA
- IT-716-M2: Furniture installed in Offices, purchased cabling received
- DMTC-8100-2130: 100G ring operating at 98.0% availability - Complete
- S19F: S19 Complete
- DM-SUIT-7: Mapping between SUIT systems & NCSA auth system
- DM-SUIT-10: SUIT deployment procedure
Due in April 2019¶
- DLP-36: Santiago - Miami Early Integration Ready
- DMTC-8100-2112: Miami - Boca Raton path diverse fiber - Complete
Due in March 2019¶
- DM-NCSA-16: Perform ISR processing on ComCam-scale data.
- DMTC-8000-0870: Report on functional fiber, including uptime, 1st year functional milestone - Complete
Due in February 2019¶
- DM-NCSA-3: Provide database for metadata, provenance, location and demonstrate ingest at small scale
- DM-NCSA-4: Minimal support for the small operational schema including file metadata and provenance for every file, and record of in
- IT-718-M: Base Center Full Occupancy
- LDM-503-02: Test report: HSC reprocessing
- LDM-503-04: Test report: Aux Tel DAQ integration functionality test
- LDM-503-07: Test report: Camera data processing
- LDM-503-04b: Test report: Aux Tel DAQ interface Integration Verification and Spectrograph Operations Rehearsal
- DM-DRP-2: Basic visualization and quality assessment tools operational on HSC-scale data volumes.
- DM-DRP-11: Pipelines code provides supports for database ingestion of results.
Due in January 2019¶
- DM-AP-8: Advanced ISR, including ghost and linear feature masking, correction for the Brighter-Fatter effect and compensation for pixel response non-uniformity.
Due in November 2018¶
- IT-716-M: Base Center Beneficial Occupancy
- F18F: F18 Complete
- DM-SUIT-8: SUIT portal integrated with workspace
- DM-DRP-19: QA metrics are generated during pipeline execution.
- DM-DAX-10: Per-object gather support in Butler
- DM-SQRE-2: Notebook service capabilities are suitable for the commissioning team to develop notebooks for its needs
Due in October 2018¶
- DMTC-8100-2330: FIU-CIARA Management Contract Delivery #4 Complete
- DMTC-8100-2530: Data passing test report - Complete
- DM-DRP-9: Data reduction pipeline for the Auxiliary Telescope.
Due in September 2018¶
- DM-NCSA-10: Sustained archiving service that is OCS commandable
- DM-NET-3: Initial Network Ready (Summit)
- DMTC-8200-0510: ESNet Request - Complete
- DM-NET-6: Summit LAN installed
Due in August 2018¶
Due in July 2018¶
Due in June 2018¶
- DMTC-8100-2090: 100G ring operating at 97.0% availability - Complete
- F18S: F18 Start
- DM-AP-7: Basic instrument signature removal (ISR) capability.
- DM-DRP-3: PSF-homogenized coadd construction.
- DM-DRP-5: Camera package supporting the LSST Camera.
- DM-DRP-38: Camera package supporting the Commissioning Camera.
Due in May 2018¶
- DMTC-8000-0836: La Serena to Santiago with live traffic and uptime over LSST Lambda Ready - Complete
- S18F: S18 Complete
Due in April 2018¶
- DMTC-8100-2490: First light test report - Complete Contract
Due in March 2018¶
- DM-NCSA-5: Level 1 archiving system able to acquire pixel data from the Aux Tel DAQ, header metadata via OCS, assemble FITS image,
- DM-NCSA-6: Ability to transfer files originating from Tucson to NCSA and ingest files at NCSA, including metadata and provenance
- DM-NCSA-7: Capability to paint displays for Tucson and NCSA
- DM-NET-2: Mountain - Base Network Functional 2 x 100 Gbps
- DLP-61: La Serena – Santiago link Ready
- DLP-44: La Serena to Santiago with test traffic AURA DWDM LSST Fiber
- DMTC-8000-0826: Intermediate traffic testing and report - Complete
- DLP-40: Summits-Gatehouse Initial Capability Ready
- DLP-65: Mountain - Base LSST and AURA DWM End Node Installation and Test Ready
- DM-DRP-32: Object classification system available.
- DM-DAX-11: Transformed EFD schema
Due in February 2018¶
- No milestones due.
Due in January 2018¶
- DM-DRP-16: Global photometric fitting (e.g. Burke et al. Forward Global Calibration Method).
Due in December 2017¶
- DM-NCSA-27: Deliver header service code
- DM-NCSA-29: Deliver IIP image client code
- DMTC-4500-0010: Start NCSA S18
- S18S: S18 Start
- LSST-1160: Header Service Integration
- LSST-1190: Control Interfaces Verification: Single Visit
- LSST-1200: Interface Verification: Single Visit
- LSST-1220: EFD ETL Under DM Control
- DLP-837: AP-ready Butler Framework
Due in November 2017¶
- DLP-864: Coordination with NCSA/CC-IN2P3 JCC
- DLP-368: Initial AP DMCS
- DLP-459: Qserv capability to hold data reduced at NCSA
- DLP-458: Ingest of bulk data from real cameras to ComCam scale
- DLP-457: Support runs on real cameras data and ImSim data
- DLP-442: Procure infrastructure for Base Center to meet FY18 goals
- DLP-433: Procure infrastructure for Archive Center to FY18 scale
- DMTC-8000-0818: Acceptance Test with Equipment Installed - Complete
- DMTC-7400-2510: REUNA La Serena - Santiago Optical Channel in operation - Complete
- DMTC-7400-2130: End of commissioning. Acceptance of fiber connection - Complete
- F17F: F17 Complete
- LDM-503-01: Test report: Science Platform with WISE data in PDAC
- LDM-503-03: Test report: Alert generation validation
- DM-SUIT-1: Search and display WISE sources (objects) in PDAC
- DM-SUIT-4: Multiple data traces in chart space
- DLP-207: Extra LSST query capabilities in web UI
- DLP-205: LSST web UI search external catalog
- DLP-222: Provide time-domain data view
- DM-DRP-14: Insertion of simulated sources into the data stream to check pipeline performance.
- DM-DRP-18: Initial multi-band deblending algorithm available.
- DM-DAX-1: WISE data ingest to PDAC
- DM-DAX-6: Prototype level 1 database
- DLP-473: Async Queries in Qserv
- DLP-725: Working Prototype of AP/L1 Database
- DLP-344: Release SQuaSH-in-a-box automated deployment platform
- DLP-352: Metrics of Interest integrated in running stack or post-tests
Due in October 2017¶
- DMTC-7400-2480: AURA DWDM equipment in operation - Complete
Due in September 2017¶
- DM-NCSA-28: IIP control code
- DMTC-7400-2330: LSST and AURA summit to base DWDM equipment - Complete
- DMTC-8100-2290: FIU-CIARA Management Contract Delivery #3 Complete
Due in August 2017¶
- DMTC-7400-2090: Report on functional fiber connections, including AURA equipment - Complete
- DLP-558: LSST Software Release 7.1 Complete
- DM-AP-1: Basic single frame measurement pipeline.
- DM-AP-2: Alard & Lupton-style image differencing.
- DM-AP-3: Point source & dipole measurement on difference images.
- DM-AP-4: DIASource association
- DM-AP-5: DIAObject generation
- DM-DRP-6: Camera package supporting the Auxiliary Telescope.
- DM-SQRE-1: Project internal Jupyter notebook service
Due in July 2017¶
- DMTC-7400-2420: REUNA La Serena - Santiago DWDM equipment - Complete
- DM-SUIT-2: Search WISE coaded data single exposure images in PDAC (the images are from IRSA at IPAC, not NCSA)
- DM-DAX-2: Query service supporting IVOA TAP protocol, w/ support for asynchronous queries
Due in June 2017¶
- DMTC-7400-2250: End of commissioning and Acceptance - Complete
- DMTC-8100-2474: Agreement with Monet Cable Partner signed Complete
- F17S: F17 Start
Due in May 2017¶
- DM-NCSA-1: Provide regular reprocessing service for HSC data
- DM-NCSA-2: Provide access to results of regular reprocessing (NB the form this takes depends upon available DAX functionality)
- DLP-538: LSE-130 Data items Exchanged between Cam & DM - Phase 3
- DMTC-0000-3000: LSST Software Release S17 Complete
- S17F: S17 Complete
- DM-DRP-1: HSC merger complete: all functionality deployed for the most recent HSC data release processing is now available within the LSST stack.
- DM-DRP-4: Calibration product generation in support of basic ISR.
- DLP-736: Performance and capability enhancements in support of catalog use cases
- DLP-152: Initial PSF-matched image coaddition available
- DLP-472: Qserv Data Distribution
Due in April 2017¶
- DMTC-8200-0480: VLAN design finalized Miami-NCSA - Complete
Due in March 2017¶
- No milestones due.
Due in February 2017¶
- DLP-37: Summits-Gatehouse Fiber Ready
- DMTC-7400-2210: Fiber delivery by Telefonica - Complete
- DLP-567: LSST Software Release 7.0 Complete
Due in January 2017¶
- DMTC-8000-0806: 3T Fiber Installation Certification and Acceptance Test - Complete
Due in November 2016¶
- DLP-847: Meet camera DAQ/OCS milestones for FY16
- DLP-366: Mid-scale processing of eligible camera data
- DLP-412: Monitor development cluster
- DMTC-0000-0030: LSST Software Release F16 Complete
- DLP-871: Firefly server side code refactor
Due in October 2016¶
- No milestones due.
Due in September 2016¶
- DMTC-8100-2050: 100G ring operating at 95.0% availability - Complete
- DMTC-8100-2250: FIU-CIARA Management Contract Delivery #2 Complete
- DLP-544: LSE-72 OCS-DM master interface - Phase 3
- DM-SUIT-3: Time series analysis tool for WISE data
Due in August 2016¶
Due in June 2016¶
- DLP-63: Vendor selection Ready
- DMTC-7400-2290: Final Selection of equipment vendor - Complete
Due in May 2016¶
- DMTC-0000-0020: LSST Software Release X16 Complete
- DLP-694: Prototype Brighter-Fatter correction available
Due in April 2016¶
- DLP-45: Delivery of “functional Pre-operations Link” (at least 4Gbps), Ready
- DMTC-8000-0910: Delivery of 4Gbs link from La Serena to Santiago Ready - Complete
Due in March 2016¶
- DMTC-7400-2050: Fiber delivery - Complete
Due in February 2016¶
- DLP-469: Coordination with NCSA/CC-IN2P3 JCC
- DLP-358: Refinement of facility integration plan and traceability of science and operational requirements
- DLP-364: Build prototype production sequence for the DMCS
- DLP-850: Prototype authentication/authorization system complete
- DLP-405: Investigate CAS integration with Internet2 AAA tools
- DLP-411: Monitor OpenStack
- DLP-424: Integration of DevOps to OpenStack
- DLP-471: Refresh sizing model
- DLP-431: Refinement of facility integration plan and traceability of science and operational requirements
- DLP-566: LSST Software Release 6.0 Complete
- DLP-872: Convert major portion of GWT in Firefly to pure JavaScript
- DLP-486: Prototype merge & deduplication in tract & patch overlaps
- DLP-103: Prototype multi-coadd peak association available
- DLP-100: Consistent multi-band deblending available
- DLP-649: Shared Scans
- DLP-345: Prototype metrics collection system deployed
- DLP-351: Intermediate Performance Metrics routinelly calculated and published
- DLP-337: Release new stack documentation infrastructure
Due in January 2016¶
- DLP-452: Support datasets on basic file system infrastructure with apropos policies
- DLP-41: Mountain - Base Fiber Path Ready
- DMTC-7400-2170: Gatehouse to Summit contract signed; Design Ready - Complete
- DLP-276: Dipole measurement suite
Due in December 2015¶
- DLP-43: Fiber Delivery Ready
- DMTC-8000-0760: Technical Implementation plan of fiber connection (primary link) - Complete
- DMTC-7400-0815: La Serena-Gatehouse path design Ready
- DMTC-7400-2010: Gatehouse to La Serena path design Ready - Complete
- DLP-288: HSC merger complete
- DLP-700: Galaxy shear fitting parameters available
- DLP-342: Publish updated introductory software guide to developing with the stack
- DLP-341: Deploy stack user support and discussion forum
Due in November 2015¶
Due in October 2015¶
- DMTC-8100-2010: First Data passed on 100G ring without errors - Complete
- DLP-528: Archive Site Ready for Equipment Configuration
- DLP-275: Deliver document on effects of DCR
- DLP-805: Distributed Database and Table Management
Due in September 2015¶
Due in August 2015¶
- DLP-356: Set up Joint Coordination Council (JCC) for coordination with satellite processing center
- DLP-355: Establish MOA with CC-IN2P3 satellite processing center
- DLP-361: Build prototype AP DMCS, including events
- DLP-404: Identify candidate security packages
- DLP-410: Implement Puppet for system configuration management
- DLP-415: Evaluate iRODS, Datacat, and similar file system management technologies
- DLP-423: DevOps assessment
- DLP-430: Initial refinement of facility integration plan
- DLP-556: LSST Software Release 5.1 Complete
- DLP-218: Provide API for image display in Firefly
- DLP-216: Provide basic APIs to use Firefly visualization components
- DLP-503: Prototype direct coaddition
- DLP-502: Prototype image artifact identification available
- DLP-25: Prototype Web Service for SUI
- DLP-340: Operating system testing for public stack releases increased
- DLP-334: SQuaRE release improved or changed CI system
Due in July 2015¶
Due in June 2015¶
Due in May 2015¶
Due in April 2015¶
- No milestones due.
Due in March 2015¶
Due in February 2015¶
Due in December 2014¶
Due in November 2014¶
Due in September 2014¶
Due in August 2014¶
- DLP-578: Propose a workspace structure for discussion.
- DLP-574: Evaluate best-of-breed tools. Technology exploration.
- DLP-575: Evaluate best-of-breed tools. Technology exploration.
- DLP-576: Evaluate best-of-breed tools. Technology exploration.
- DLP-577: Evaluate best-of-breed tools. Technology exploration.
- DLP-639: Re-design camera geometry classes
- DLP-638: Refactor AFW R&D Code
- DLP-588: AFW R&D code refactored
- DLP-715: Fundamental centroid and shape measurements
- DLP-697: Single epoch CModel minimization
- DLP-696: Single epoch Sersic model fitting
- DLP-836: New logging for DM
- DLP-835: New xrootd client
- DLP-834: Automated Testbed for Qserv
Milestones by WBS¶
02C.00: Data Management Level 2 Milestones¶
DLP-554: LSST Software Release 4.0 Complete¶
- WBS: 02C.00
- Level: 2
- Successors: DLP-556
- Due: 2014-09-02
- Completed: 2014-09-30
Warning
No description available
DLP-555: LSST Software Release 5.0 Complete¶
- WBS: 02C.00
- Level: 2
- Due: 2015-02-26
- Completed: 2015-03-06
Warning
No description available
DLP-559: Mountain - Base Network Functional 1 Gbps¶
- WBS: 02C.00
- Level: 1
- Successors: DM-NET-2
- Due: 2015-06-02
- Completed: 2015-06-01
Warning
No description available
DLP-556: LSST Software Release 5.1 Complete¶
- WBS: 02C.00
- Level: 2
- Predecessors: DLP-400, DLP-554
- Successors: DLP-557, DLP-566
- Due: 2015-08-31
- Completed: 2015-09-01
Warning
No description available
DLP-528: Archive Site Ready for Equipment Configuration¶
- WBS: 02C.00
- Level: 1
- Due: 2015-10-01
- Completed: 2015-10-01
This is complete in. data/pmcs/201904-ME.xls.
DLP-566: LSST Software Release 6.0 Complete¶
- WBS: 02C.00
- Level: 2
- Predecessors: DLP-364, DLP-389, DLP-556, DLP-486, DLP-103, DLP-100
- Successors: DLP-557
- Due: 2016-02-29
- Completed: 2016-07-12
Warning
No description available
DMTC-0000-0020: LSST Software Release X16 Complete¶
- WBS: 02C.00
- Level: 2
- Predecessors: DLP-694
- Due: 2016-05-31
- Completed: 2016-07-12
Warning
No description available
DLP-541: LSE-68 Camera-DM Image data interfaces - Phase 3¶
- WBS: 02C.00
- Level: 2
- Successors: S17S
- Due: 2016-07-05
- Completed: 2016-10-31
Complete with LCR-1788 June 2019.
DLP-557: LSST Software Release 6.1 Complete¶
- WBS: 02C.00
- Level: 2
- Predecessors: DLP-556, DLP-566, DLP-579
- Successors: DLP-558
- Due: 2016-08-31
- Completed: 2016-08-31
Warning
No description available
DLP-544: LSE-72 OCS-DM master interface - Phase 3¶
- WBS: 02C.00
- Level: 2
- Successors: DLP-558
- Due: 2016-09-30
- Completed: 2016-10-31
Warning
No description available
DMTC-0000-0030: LSST Software Release F16 Complete¶
- WBS: 02C.00
- Level: 2
- Successors: DLP-847, DLP-366, DLP-412, DLP-871
- Due: 2016-11-30
- Completed: 2016-11-30
Warning
No description available
S17S: S17 Start¶
- WBS: 02C.00
- Level: 2
- Predecessors: DLP-850, DLP-405, DLP-541, DLP-871
- Successors: S17F
- Due: 2016-12-01
- Completed: 2016-12-01
Warning
No description available
DLP-567: LSST Software Release 7.0 Complete¶
- WBS: 02C.00
- Level: 2
- Due: 2017-02-28
- Completed: 2017-02-28
Warning
No description available
DLP-538: LSE-130 Data items Exchanged between Cam & DM - Phase 3¶
- WBS: 02C.00
- Level: 2
- Predecessors: DMTC-0000-3000, S17F
- Successors: DLP-558
- Due: 2017-05-31
- Completed: 2017-05-31
approval of LCR-1494 in June 2019 allows this to be closed, LSE-400 [15] covers the items.
DMTC-0000-3000: LSST Software Release S17 Complete¶
Warning
No description available
S17F: S17 Complete¶
- WBS: 02C.00
- Level: 2
- Predecessors: S17S
- Successors: DLP-61, DLP-538, DLP-736, DLP-152, DLP-473, DLP-472
- Due: 2017-05-31
- Completed: 2017-05-31
Warning
No description available
F17S: F17 Start¶
Warning
No description available
DLP-558: LSST Software Release 7.1 Complete¶
- WBS: 02C.00
- Level: 2
- Predecessors: DLP-544, DLP-557, DLP-538
- Successors: DLP-551
- Due: 2017-08-31
- Completed: 2017-08-31
Warning
No description available
F17F: F17 Complete¶
- WBS: 02C.00
- Level: 2
- Predecessors: DLP-847, DLP-366, F17S
- Successors: DLP-368, DLP-459, DLP-458, DLP-457, DLP-442, DLP-433, DLP-207, DLP-205, DLP-222, DLP-473, DLP-725, DLP-344, DLP-352
- Due: 2017-11-30
- Completed: 2017-11-30
Warning
No description available
LDM-503-01: Test report: Science Platform with WISE data in PDAC¶
- WBS: 02C.00
- Level: 2
- Test specification: LDM-540 [9] v1.0 S3.1 (LSP-00)
- Predecessors: DM-SUIT-1, DM-SUIT-2, DM-SUIT-3, DM-SUIT-4, DM-DAX-1, DM-SQRE-1
- Successors: LDM-503-07
- Due: 2017-11-30
- Completed: 2018-05-30
This test demonstrates the deployment of the Portal and API Aspects of the LSST Science Platform (LSE-319 [13], LDM-542 [11], LDM-554 [10]) to serve all-sky precursor data, including catalogs totaling of order 50–100 billion rows, in a prototype LSST Data Access Center hosted in the LSST Data Facility at NCSA.
LDM-503-03: Test report: Alert generation validation¶
- WBS: 02C.00
- Level: 2
- Test specification: LDM-533 [1] v1.1 S3.1 (AG-00)
- Predecessors: DM-AP-1, DM-AP-2, DM-AP-3, DM-AP-4, DM-AP-5, DM-DAX-6
- Successors: LDM-503-05
- Due: 2017-11-30
- Completed: 2017-12-01
This test demonstrates the successful execution of a prototype Alert Generation science payload (LDM-148 [16], LDM-151 [22]), processing data from precursor surveys at a relatively small scale using compute resources at the LSST Data Facility at NCSA.
S18S: S18 Start¶
- WBS: 02C.00
- Level: 2
- Predecessors: DLP-368, DLP-412, DLP-459, DLP-458, DLP-457, DLP-207, DLP-205, DLP-222, DLP-725, DLP-352
- Successors: S19S
- Due: 2017-12-01
- Completed: 2017-12-01
Warning
No description available
LSST-1160: Header Service Integration¶
- WBS: 02C.00
- Level: 2
- Predecessors: DM-NCSA-27
- Successors: LSST-1190
- Due: 2017-12-29
- Completed: 2018-03-31
Warning
No description available
LSST-1190: Control Interfaces Verification: Single Visit¶
- WBS: 02C.00
- Level: 2
- Predecessors: DM-NCSA-28, LSST-1160
- Successors: LSST-1200, LSST-1220
- Due: 2017-12-29
- Completed: 2018-03-30
Warning
No description available
LSST-1200: Interface Verification: Single Visit¶
- WBS: 02C.00
- Level: 2
- Predecessors: DM-NCSA-29, LSST-1190
- Successors: F18S, LDM-503-06
- Due: 2017-12-29
- Completed: 2018-04-05
Warning
No description available
LSST-1220: EFD ETL Under DM Control¶
- WBS: 02C.00
- Level: 2
- Predecessors: LSST-1190
- Successors: LSST-1580
- Due: 2017-12-29
- Completed: 2019-03-29
Warning
No description available
S18F: S18 Complete¶
- WBS: 02C.00
- Level: 2
- Predecessors: DLP-864
- Successors: DLP-33, DM-DRP-3, DM-DRP-5, DM-DRP-8, DM-DRP-9, DM-DRP-11, DM-DRP-17, DM-DRP-19, DM-DRP-38
- Due: 2018-05-31
- Completed: 2018-05-31
Warning
No description available
F18S: F18 Start¶
- WBS: 02C.00
- Level: 2
- Predecessors: LSST-1200
- Successors: F19S, LDM-503-05, DM-AP-6, DM-AP-7, DM-AP-9
- Due: 2018-06-01
- Completed: 2018-06-01
Warning
No description available
DLP-551: LSST Software Release 8.1 Complete, Ready for Commissioning Camera¶
- WBS: 02C.00
- Level: 1
- Predecessors: DLP-558
- Successors: DLP-552, COMC-0100
- Due: 2018-08-31
- Completed: 2018-07-12
Warning
No description available
F18F: F18 Complete¶
- WBS: 02C.00
- Level: 2
- Successors: DM-NCSA-11, DLP-464, DLP-466, DM-AP-8, DM-DRP-37, DM-DRP-29, DM-DAX-8, DM-DAX-9, DM-DAX-10
- Due: 2018-11-30
- Completed: 2018-11-30
Warning
No description available
S19S: S19 Start¶
Warning
No description available
LDM-503-02: Test report: HSC reprocessing¶
- WBS: 02C.00
- Level: 2
- Test specification: LDM-534 [21] v3.1 S3.1 (DRP-00)
- Predecessors: DM-NCSA-1, DM-NCSA-2, DM-NCSA-3, DM-AP-1, DM-DRP-1, DM-DRP-2
- Successors: DM-NCSA-4, LDM-503-07
- Due: 2019-02-28
- Completed: 2017-12-01
This test demonstrates the successful execution of a prototype Data Release Production science payload (LDM-148 [16], LDM-151 [22]), processing data from precursor surveys at a relatively small scale using compute resources at the LSST Data Facility at NCSA.
LDM-503-04: Test report: Aux Tel DAQ integration functionality test¶
- WBS: 02C.00
- Level: 2
- Test specification: LDM-538 [7] v1.0 S4.1 (RAS-00-00)
- Predecessors: DM-NCSA-4
- Successors: LDM-503-10, LDM-503-04b
- Due: 2019-02-28
- Completed: 2018-06-29
This test demonstrates that LSST data acquisition system can capture raw data from instrumentation and construct a well-formed image with proper headers.
LDM-503-07: Test report: Camera data processing¶
- WBS: 02C.00
- Level: 2
- Test specification: DMTR-112 [19] [DM-16072]
- Predecessors: LDM-503-01, LDM-503-02, DM-DRP-4
- Successors: LSST-1470, DLP-552, LDM-503-09
- Due: 2019-02-28
- Completed: 2019-01-17
This test demonstrates that the LSST Science Pipelines can be successfully used to load and perform basic processing of data from the LSST Camera test systems. In the process, it establishes that data is properly made available at the LSST Data Facility at NCSA, and is accessible through the LSST Science Platform.
LDM-503-04b: Test report: Aux Tel DAQ interface Integration Verification and Spectrograph Operations Rehearsal¶
- WBS: 02C.00
- Level: 2
- Test specification: LDM-538 [7] v1.0 S4.4 (RAS-00-20)
- Predecessors: DM-NCSA-27, DM-NCSA-5, DM-NCSA-6, DM-NCSA-7, LDM-503-04
- Successors: LDM-503-08
- Due: 2019-02-28
- Completed: 2018-06-29
This test demonstrates that the well-formed image generated in LDM-503-04 can be written to the permanent record of the survey.
S19F: S19 Complete¶
- WBS: 02C.00
- Level: 2
- Successors: DLP-46, DLP-877, DLP-876, S20S, DM-SUIT-7, DM-SUIT-10
- Due: 2019-05-31
- Completed: 2019-05-31
Time-based milestone marking the completion of the Spring 2019 development cycle.
F19S: F19 Start¶
Warning
No description available
LDM-503-10a: Science Platform: TAP service with federated SSO A&A¶
- WBS: 02C.00
- Level: 2
- Test specification: DMTR-161 [8] [DM-19211]
- Predecessors: DM-DAX-2
- Successors: LDM-503-10b
- Due: 2019-07-29
- Completed: 2019-12-31 [DM-19209]
This test demonstrates the successful integration of a single-sign-on federated authentication system, and a basic authorization system, with the three Aspects of the LSST Science Platform (Portal, Notebook, and API), with the API Aspect containing at least a TAP service.
DLP-552: LSST Software Release 9.1 Complete, Ready for Full Camera¶
- WBS: 02C.00
- Level: 1
- Predecessors: DM-NCSA-11, DLP-551, LDM-503-07
- Successors: LSST-1470, LDM-503-09
- Due: 2019-08-30
- Completed: 2019-08-30
This pipeline software release will precede LDM-503-12a. This will have all functionality required to process data from LSSTCam. It will not have the full functionality for data release processing.
LDM-503-08b: Small Scale CCOB Data Access¶
- WBS: 02C.00
- Level: 2
- Test specification: DMTR-102 [6] [DM-16073]
- Predecessors: A5860
- Successors: LDM-503-09
- Due: 2019-11-08
- Completed: 2019-07-15 [DM-17118]
This test demonstrates the integration of the CCOB with the permanent record of the survey.
F19F: F19 Complete¶
- WBS: 02C.00
- Level: 2
- Predecessors: F19S
- Successors: F20S, S20S, DM-STAFF
- Due: 2019-11-27
- Completed: 2019-11-29
Time-based milestone marking the completion of the Fall 2019 development cycle.
DM-STAFF: Staffing Checkpoint¶
- WBS: 02C.00
- Level: 2
- Predecessors: F19F
- Successors: LDM-503-13
- Due: 2019-11-27
- Completed: 2019-11-29
DM Management evaluate current DM staffing against project schedule and budget. If there is a shortfall through mid-2022 (the “ops gap”), this is the point at which we need to fill it.
S20S: S20 Start¶
- WBS: 02C.00
- Level: 2
- Predecessors: S19S, S19F, F19F
- Successors: S21S, S20F, LDM-503-EFDb
- Due: 2019-12-02
- Completed: 2019-12-02
Warning
No description available
DLP-533: Base Center Integration Complete¶
- WBS: 02C.00
- Level: 1
- Successors: COMC-1564, COMC-0100, COMC-0620-2090
- Due: 2020-05-13
- Completed: 2020-02-28
This milestone represents the availabilitu of the base center in Las Serena. This includes DM staging machines, the comissioning cluster. It also includes the Chilean Data Access center machines. The later will only be deployed after the US DAC is up.
S20F: S20 Complete¶
- WBS: 02C.00
- Level: 2
- Predecessors: S20S
- Successors: F20S, S21S, DM-AP-18
- Due: 2020-05-29
- Completed: 2020-05-29
Time-based milestone marking the completion of the Spring 2020 development cycle.
LDM-503-05: Test report: Alert distribution validation¶
- WBS: 02C.00
- Level: 2
- Test specification: LDM-533 [1] v2.0 SS 4.7–4.9 (test cases LVV-T216, LVV-T217, LVV-T218)
- Predecessors: DM-NCSA-8, DM-NCSA-9, F18S, LDM-503-03
- Successors: LDM-503-09
- Due: 2020-05-29
- Completed: 2018-07-17
This test demonstrates that a full-LSST-scale (10,000 messages every 39 seconds) alert stream can be distributed to end users. It further shows that simple filters based on alert contents can be applied to that stream.
LDM-503-09a: Test report: Pipelines Release Fall 2018¶
- WBS: 02C.00
- Level: 2
- Test specification: DMTR-111 [20] [DM-16076]
- Predecessors: DM-AP-2, DM-AP-3, DM-AP-6, DM-AP-7, DM-AP-9, DM-DRP-3, DM-DRP-5, DM-DRP-7, DM-DRP-16, DM-DRP-17, DM-DRP-32, DM-DRP-38
- Successors: LDM-503-09, LDM-503-11
- Due: 2020-05-29
- Completed: 2019-04-12 [DM-17121]
This milestone describes a software release of the LSST Science Pipelines in support of activities in late 2018 and early 2019. The contents of the release are described in LDM-564 [17]. The release will be accompanied by a characterization report.
F20S: F20 Start¶
- WBS: 02C.00
- Level: 2
- Predecessors: S20F, F19F
- Successors: DM-NCSA-23, F21S, F20F, DM-AP-10, DM-DRP-22, DM-DRP-24
- Due: 2020-06-01
- Completed: 2020-06-01
Time-based milestone marking the start of the Fall 2020 development cycle.
LDM-503-06: Test report: DM ComCam interface verification readiness¶
- WBS: 02C.00
- Level: 2
- Test specification: DMTR-171 [4] [DM-16074]
- Predecessors: DM-NCSA-10, DM-NCSA-11, LSST-1200, T&SC-6500-9000, T&SC-7900-2430
- Successors: LSST-1510, LDM-503-10, LDM-503-11a
- Due: 2020-06-03
- Completed: 2020-06-30 [DM-17119]
This milestone records successful transfer of an image equivalent to one raft from the DAQ at the summit to reliable storage in the LSST Data Facility at NCSA, from where it will be made available for scientific evaluation through the LSST Science Platform.
LDM-503-08: Test report: Spectrograph data acquisition¶
- WBS: 02C.00
- Level: 2
- Test specification: DMTR-121 [5] [DM-16455]
- Predecessors: CAMM8300, DM-NCSA-13, DM-NCSA-14, DM-NCSA-15, DM-NET-2, DM-NET-3, DM-NET-6, LDM-503-04b, DM-DRP-6
- Successors: LDM-503-10, LDM-503-11
- Due: 2020-11-30
- Completed: 2019-12-31 [DM-17131]
This test demonstrates data acquisition from the Auxiliary Telescope spectrograph, transmission of all image files with associated metadata to NCSA for screening, and then further processing if needed.
LDM-503-09: Test report: Ops rehearsal for commissioning #1¶
- WBS: 02C.00
- Level: 2
- Test specification: LDM-643 [12] [DM-16075]
- Predecessors: DM-NCSA-16, A4680, A4860, DLP-552, LDM-503-05, LDM-503-07, LDM-503-08b, LDM-503-09a, DM-SUIT-5, DM-DAX-2, DM-DAX-5, DM-DAX-9, DM-SQRE-2, A2370
- Successors: LDM-503-11
- Due: 2020-11-30
- Completed: 2019-10-07 [DM-17120]
This milestone represents the completion of a multi-day exercise in which (simulated) observations are performed and data is processed in as close to an operational mode as is possible at this stage in construction. In particular, it will demonstrate transfer, archiving and intestion of raw data; offline processing of calibration and science data; and curation of the resultant data products.
LDM-503-10: Test report: DAQ validation¶
- WBS: 02C.00
- Level: 2
- Test specification: DMTR-181 [3] [DM-16193]
- Predecessors: IT-725-M, LDM-503-04, LDM-503-06, LDM-503-08
- Successors: LDM-503-11
- Due: 2020-11-30
- Completed: 2020-06-22 [DM-17122]
Test of the extended data acquisition (DAQ) network in Chile from the Summit to the Base Data Center.
LDM-503-11b: Test report: Pipelines Release Fall 2019¶
- WBS: 02C.00
- Level: 2
- Test specification: DMTR-192 [18] [DM-16197]
- Predecessors: DM-AP-8, DM-DRP-9, DM-DRP-14, DM-DRP-15, DM-DRP-18, DM-DRP-19
- Successors: LDM-503-11, LDM-503-13a, LDM-503-11a
- Due: 2020-12-01
- Completion pending [DM-17126]
This milestone describes a software release of the LSST Science Pipelines in support of activities in late 2019 and early 2020. The contents of the release are described in LDM-564 [17]. The release will be accompanied by a characterization report.
LDM-503-11a: ComCam Ops Readiness¶
- WBS: 02C.00
- Level: 2
- Test specification: Undefined [DM-16196]
- Predecessors: DM-NCSA-16, DM-NCSA-20, DM-NCSA-21, DM-NCSA-22, LDM-503-06, LDM-503-11b, DM-SUIT-10
- Successors: LDM-503-12
- Due: 2020-12-01
- Completion pending [DM-17125]
Demonstrate that all DM functionality required to support ComCam operations has been delivered.
DLP-526: Archive Center Integration Complete¶
- WBS: 02C.00
- Level: 1
- Successors: COMC-1664
- Due: 2021-01-28
- Completion pending
This milestone represents the availability of an arhcive center to host LSST DR1 dat. This includes an scince platfirm interface with the implied services for Data Access, a portal and Notebooks.
F20F: F20 Complete¶
- WBS: 02C.00
- Level: 2
- Predecessors: F20S, DM-DRP-11, DLP-837
- Successors: DLP-465, DLP-468, DLP-467, F21S, S21S, LDM-503-11, DM-DRP-30, DM-DRP-25, DM-DRP-34, DM-DAX-12, DM-DAX-14, DM-SQRE-6, DM-SQRE-7
- Due: 2021-06-02
- Completion pending
Time-based milestone marking the completion of the Fall 2020 development cycle.
LDM-503-14a: Science Platform ready for DP0¶
- WBS: 02C.00
- Level: 2
- Test specification: Undefined [DM-26340]
- Predecessors: S21S
- Successors: DM2, LDM-503-12a
- Due: 2021-06-03
- Completion pending [DM-26349]
Take the output of a DRP-like, BG3-based, SDM-ified data production and, without a great deal of manual labor, make the resulting image and catalog data available to users through the aspects of the LSP. This includes the generation of image metadata table content for the LSP.
LDM-503-11: Ops rehearsal for commissioning #2¶
- WBS: 02C.00
- Level: 2
- Test specification: LDM-643 [12] [DM-16195]
- Predecessors: DM-NCSA-16, DLP-468, DLP-467, DM-NET-4, F20F, LDM-503-08, LDM-503-09, LDM-503-10, LDM-503-11b, LDM-503-09a
- Successors: LDM-503-12
- Due: 2021-06-04
- Completion pending [DM-17124]
Template generation, including code required to build templates in both Data Release and Alert Production science payloads, can now product templates which are corrected for the effects of Differential Chromatic Refraction (DCR), as described in LDM-151 [22] §6.18. Further, noise in image differences can be “decorrelated”, as described in LDM-151 [22] §6.19.1. Both of these represents initial capabilities, providing realistic interfaces, data-flows and products; ongoing refinement of the algorithms being used is expected.
F21S: F21 Start¶
- WBS: 02C.00
- Level: 2
- Predecessors: F20S, S21F, F20F
- Successors: F21F, DM-DRP-23
- Due: 2021-07-05
- Completion pending
Warning
No description available
S21S: S21 Start¶
- WBS: 02C.00
- Level: 2
- Predecessors: S20S, S20F, F20F
- Successors: S22S, S21F, LDM-503-14a
- Due: 2021-07-05
- Completion pending
Warning
No description available
S21F: S21 Complete¶
- WBS: 02C.00
- Level: 2
- Predecessors: S21S
- Successors: DM7, F21S, S22S, LDM-503-13a, DM-DAX-13
- Due: 2021-08-30
- Completion pending
Time-based milestone marking the completion of the Spring 2021 development cycle.
LDM-503-13a: Test report: Pipelines Release Fall 2020¶
- WBS: 02C.00
- Level: 2
- Test specification: Undefined [DM-16200]
- Predecessors: S21F, LDM-503-11b, DM-AP-11, DM-AP-12, DM-AP-13, DM-DRP-22, DM-DRP-26, DM-DRP-27, DM-DRP-28, DM-DRP-30, DM-DRP-25, DM-DRP-34
- Successors: LDM-503-13, LDM-503-14, LDM-503-15a
- Due: 2021-08-30
- Completion pending [DM-17129]
This milestone describes a software release of the LSST Science Pipelines in support of activities in late 2020 and early 2021. The contents of the release are described in LDM-564 [17]. The release will be accompanied by a characterization report.
LDM-503-10b: Large Scale CCOB Data Access¶
- WBS: 02C.00
- Level: 2
- Test specification: DMTR-182 [2] [DM-16194]
- Predecessors: CAMM8040, CAMM8080, CAMM8300, LDM-503-10a
- Successors: LSST-1580
- Due: 2021-08-31
- Completion pending [DM-17123]
Demonstrate the ability to transfer data from the CCOB with 21 rafts from SLAC and ingested at NCSA and make available through an instance of the LSP.
LDM-503-EFDa: Engineering Facility Database at the summit capturing and enabling access to all telemetry with M1/M3 active¶
- WBS: 02C.00
- Level: 2
- Test specification: Undefined [DM-26342]
- Successors: LDM-503-12a, LDM-503-EFDb
- Due: 2021-10-28
- Completion pending [DM-26348]
An instance of the Engineering and Facility Database at the summit capturing and enabling access to all telemetry, including from an active M1M3. This may be distinct from the Auxiliary Telescope EFD instance. Demonstrate the ability to run for five days, allowing data retrieval and plotting via notebooks.
S22S: S22 Start¶
- WBS: 02C.00
- Level: 2
- Predecessors: S21S, S21F, F21F
- Successors: DM-NCSA-26, DM-PORTAL, DM-CLOUD
- Due: 2021-12-01
- Completion pending
Warning
No description available
LDM-503-15a: Test report: Pipelines Release Fall 2021¶
- WBS: 02C.00
- Level: 2
- Test specification: Undefined [DM-17136]
- Predecessors: LDM-503-13a, DM-AP-15, DM-AP-16, DM-AP-17
- Successors: DM9, DM11, DM12, LDM-503-17a
- Due: 2021-12-16
- Completion pending [DM-17137]
This milestone describes a software release of the LSST Science Pipelines in support of activities in late 2021 and early 2022. The contents of the release are described in LDM-564 [17]. The release will be accompanied by a characterization report.
LDM-503-12a: LSSTCam Ops Readiness¶
- WBS: 02C.00
- Level: 2
- Test specification: Undefined [DM-16199]
- Predecessors: CAMM8090, LDM-503-14a, LDM-503-EFDa, COMC-0030
- Successors: LSST-1520, DM1, LDM-503-EFDc
- Due: 2022-03-14
- Completion pending [DM-17128]
Demonstrate that all DM functionality required to support operations with the full LSST Camera has been delivered.
LDM-503-EFDb: EFD/telemetry data replicated at the LDF, stored in InfluxDB. aggregated into parquet files¶
- WBS: 02C.00
- Level: 2
- Test specification: Undefined [DM-26344]
- Predecessors: S20S, LDM-503-EFDa, COMC-0100
- Successors: LSST-1520
- Due: 2022-03-14
- Completion pending [DM-26347]
Demonstrate that EFD data from the Summit appears at the US Data Facility. Show that the Parquet files generated contain all low frequency EFD values and summaries of high frequency values.
LDM-503-EFDc: EFD data is queriable through TAP in the Science Platform¶
- WBS: 02C.00
- Level: 2
- Test specification: Undefined [DM-26345]
- Predecessors: LDM-503-12a
- Successors: LSST-1520
- Due: 2022-03-14
- Completion pending [DM-26346]
Demonstrate that engineering data for a specific observation time can be retrieved via TAP on the Science Platform or directly to a TAP tool like TopCat. Test DMS-REQ-0102 (Priority 1a) to permantely archive metadata from OCS and make availble to rights holders. Also test DMS-REQ-0358 (Priority 1a), demonstrating support of simultaneous queries.
F21F: F21 Complete¶
- WBS: 02C.00
- Level: 2
- Predecessors: F21S
- Successors: S22S, LDM-503-12, DM-AP-14
- Due: 2022-03-16
- Completion pending
Time-based milestone marking the completion of the Fall 2021 development cycle.
LDM-503-12: Ops rehearsal for commissioning #3¶
- WBS: 02C.00
- Level: 2
- Test specification: Undefined [DM-16198]
- Predecessors: F21F, LDM-503-11, LDM-503-11a, DM-SQRE-3
- Successors: LDM-503-13, LDM-503-14
- Due: 2022-03-16
- Completion pending [DM-17127]
This milestone builds upon LDM-503-11, and serves to demonstrate that all necessary procedures and workflows are in place to support commissioning activities.
LDM-503-13: Ops rehearsal for data release processing #1 (ComCam data)¶
- WBS: 02C.00
- Level: 2
- Test specification: Undefined [DM-16201]
- Predecessors: DM-NCSA-23, LDM-503-12, DM-STAFF, LDM-503-13a, COMC-0100
- Successors: LDM-503-14, LDM-503-15
- Due: 2022-03-16
- Completion pending [DM-17130]
This milestone builds upon LDM-503-12, but with its scope extended beyond procedures which are necessary in commissioning to cover the operational era.
LDM-503-14: Test report: DM Readiness for Science Verification¶
- WBS: 02C.00
- Level: 2
- Test specification: Undefined [DM-17132]
- Predecessors: LDM-503-12, LDM-503-13, LDM-503-13a, DM-SQRE-4
- Successors: COMC-0140, COMC-060200-20960
- Due: 2022-03-16
- Completion pending [DM-17133]
This milestone represents the point at which all code and/or services which are supplied by DM in support of science verification will be tested and demonstrated to meet their requirements.
DM-PORTAL: Resume development of LSP portal aspect¶
- WBS: 02C.00
- Level: 2
- Predecessors: S22S
- Successors: LSST-1580
- Due: 2022-03-17
- Completion pending
Warning
No description available
DM-CLOUD: Decide on final data facility design for DR1¶
- WBS: 02C.00
- Level: 2
- Predecessors: S22S
- Successors: LSST-1580
- Due: 2022-03-17
- Completion pending
Warning
No description available
S22F: S22 Complete¶
- WBS: 02C.00
- Level: 2
- Successors: LSST-1590
- Due: 2022-09-14
- Completion pending
Time-based milestone marking the completion of the Spring 2022 development cycle.
LDM-503-15: Ops rehearsal for data release processing #2¶
- WBS: 02C.00
- Level: 2
- Test specification: Undefined [DM-17134]
- Predecessors: DM-NCSA-24, DM-NCSA-25, LDM-503-13
- Successors: DM15, LDM-503-16
- Due: 2022-10-05
- Completion pending [DM-17135]
This milestone builds upon LDM-503-13, and will demonstrate the production of a data release under simulated operational conditions using data from science verification activities.
LDM-503-17a: Test report: Final Pipelines Delivery¶
- WBS: 02C.00
- Level: 2
- Test specification: Undefined [DM-17142]
- Predecessors: LDM-503-15a
- Successors: LDM-503-17
- Due: 2022-10-18
- Completion pending [DM-17143]
This milestone describes the final Science Pipelines release from the DM Construction Project. The contents of the release are described in LDM-564 [17]. The release will be accompanied by a characterization report.
LDM-503-16: Ops rehearsal for data release processing #3¶
- WBS: 02C.00
- Level: 2
- Test specification: Undefined [DM-17138]
- Predecessors: DM-NCSA-26, LDM-503-15
- Successors: LDM-503-17
- Due: 2023-01-05
- Completion pending [DM-17139]
This milestone builds upon LDM-503-15 to demonstrate the production of a complete data release under simulated operational conditions.
LDM-503-17: Final operations rehearsal¶
- WBS: 02C.00
- Level: 2
- Test specification: Undefined [DM-17140]
- Predecessors: LDM-503-16, LDM-503-17a
- Successors: LSST-1590
- Due: 2023-02-03
- Completion pending [DM-17141]
This milestone builds upon LDM-503-16 to demonstrate successful operation of all aspects of the DM subsystem under simulated operational conditions.
02C.03: Alert Production¶
DLP-639: Re-design camera geometry classes¶
- WBS: 02C.03.01
- Level: 3
- Predecessors: LSST-1440
- Due: 2014-08-01
- Completed: 2014-08-13
Warning
No description available
DLP-638: Refactor AFW R&D Code¶
- WBS: 02C.03.05
- Level: 3
- Predecessors: LSST-1440
- Due: 2014-08-01
- Completed: 2014-08-13
Warning
No description available
DLP-642: Camera Team using DM code¶
- WBS: 02C.03.01
- Level: 3
- Due: 2014-12-10
- Completed: 2014-12-10
Warning
No description available
DLP-644: Generalized Single Frame Astrometry Pipeline¶
- WBS: 02C.03.08
- Level: 3
- Due: 2015-02-24
- Completed: 2015-02-24
Warning
No description available
DLP-275: Deliver document on effects of DCR¶
- WBS: 02C.03.04
- Level: 3
- Successors: DLP-276
- Due: 2015-10-29
- Completed: 2016-04-08
Warning
No description available
DLP-276: Dipole measurement suite¶
- WBS: 02C.03.04
- Level: 3
- Predecessors: DLP-275
- Due: 2016-01-22
- Completed: 2016-07-12
Warning
No description available
DM-AP-1: Basic single frame measurement pipeline.¶
- WBS: 02C.03
- Level: 3
- Successors: LDM-503-02, LDM-503-03, DM-AP-10
- Due: 2017-08-31
- Completed: 2017-11-01
Warning
No description available
DM-AP-2: Alard & Lupton-style image differencing.¶
- WBS: 02C.03
- Level: 3
- Successors: LDM-503-03, LDM-503-09a, DM-AP-11
- Due: 2017-08-31
- Completed: 2017-11-01
Warning
No description available
DM-AP-3: Point source & dipole measurement on difference images.¶
- WBS: 02C.03
- Level: 3
- Successors: LDM-503-03, LDM-503-09a, DM-AP-13
- Due: 2017-08-31
- Completed: 2017-11-01
Warning
No description available
DM-AP-4: DIASource association¶
- WBS: 02C.03
- Level: 3
- Successors: LDM-503-03
- Due: 2017-08-31
- Completed: 2017-11-01
Warning
No description available
DM-AP-5: DIAObject generation¶
- WBS: 02C.03
- Level: 3
- Successors: LDM-503-03
- Due: 2017-08-31
- Completed: 2017-11-01
Warning
No description available
DM-AP-7: Basic instrument signature removal (ISR) capability.¶
- WBS: 02C.03
- Level: 3
- Predecessors: F18S, DM-DRP-4
- Successors: LDM-503-09a
- Due: 2018-06-29
- Completed: 2018-06-29
Warning
No description available
DM-AP-9: JOINTCAL1: Jointcal at a functional level¶
- WBS: 02C.03
- Level: 3
- Predecessors: F18S
- Successors: LDM-503-09a, DM-DRP-17, DM-DRP-21
- Due: 2018-07-20
- Completed: 2018-11-29
Warning
No description available
DM-AP-8: Advanced ISR, including ghost and linear feature masking, correction for the Brighter-Fatter effect and compensation for pixel response non-uniformity.¶
- WBS: 02C.03
- Level: 3
- Predecessors: F18F
- Successors: LDM-503-11b
- Due: 2019-01-04
- Completed: 2019-01-17
Warning
No description available
DM-AP-11: Difference imaging includes noise decorrelation and correction for differential chromatic refraction.¶
- WBS: 02C.03
- Level: 3
- Predecessors: DM-AP-2
- Successors: LDM-503-13a, DM-AP-12, DM-DRP-28
- Due: 2019-11-27
- Completed: 2019-10-01
Template generation, including code required to build templates in both Data Release and Alert Production science payloads, can now product templates which are corrected for the effects of Differential Chromatic Refraction (DCR), as described in LDM-151 [22] §6.18. Further, noise in image differences can be “decorrelated”, as described in LDM-151 [22] §6.19.1. Both of these represents initial capabilities, providing realistic interfaces, data-flows and products; ongoing refinement of the algorithms being used is expected.
DM-AP-6: Alert format defined & queue system available.¶
- WBS: 02C.03
- Level: 3
- Predecessors: DM-NCSA-8, DM-NCSA-9, F18S
- Successors: LDM-503-09a, DM-AP-14
- Due: 2020-05-29
- Completed: 2018-07-31
Warning
No description available
DM-AP-18: Alert packet generation¶
The AP Pipeline is now capable of generating per-DIASource alert packets, which comply with the current version of the LSST alert schema. This milestone only covers packet generation; success involves only those serialized alerts being e.g. written to disk, and does not imply that an alert transport system is available.
DM-AP-10: Advanced single frame measurement pipeline for Alert Production.¶
- WBS: 02C.03
- Level: 3
- Predecessors: F20S, DM-AP-1
- Successors: LSST-1580
- Due: 2020-12-01
- Completion pending
The Single Frame Processing system is now substantially complete and provides all functionality described in LDM-151 [22] §3.1. It supports all expected interfaces, data-flows, and products, but the details of the algorithms are expected to undergo continued refinement.
DM-AP-15: Alert distribution system fully integrated.¶
- WBS: 02C.03
- Level: 3
- Successors: DM16, LDM-503-15a, DM-AP-16
- Due: 2021-03-02
- Completion pending
The Alert Distribution system (LDM-151 [22] §3.3) is now available for deployment at the LSST Data Facility. The system is substantially complete, and supports all expected interfaces, data-flows, and products, but the details of the algorithms may undergo continued refinement.
DM-AP-12: Difference imaging is now agnostic to the PSF of the template image.¶
- WBS: 02C.03
- Level: 3
- Predecessors: DM-AP-11
- Successors: LDM-503-13a
- Due: 2021-05-07
- Completion pending
The Alert Generation science payload is now agnostic to the PSF of the template, as described in LDM-151 [22] §3.2.4. This represents an initial capability, providing realistic interfaces, data-flows and products; ongoing refinement of the algorithm being used is expected.
DM-AP-13: Trailed source measurement on difference images.¶
- WBS: 02C.03
- Level: 3
- Predecessors: DM-AP-3
- Successors: LDM-503-13a
- Due: 2021-05-07
- Completion pending
The Alert Generation science payload now provides the capability to fit a trailed point source model to detections made on difference images, as described in LDM-151 [22] §3.2.4. This represents an initial capability, providing realistic interfaces, data-flows and products; ongoing refinement of the algorithm being used is expected.
DM-AP-16: Full integration of the Alert Production system within the operational environment.¶
- WBS: 02C.03
- Level: 3
- Predecessors: DM-AP-15
- Successors: LDM-503-15a
- Due: 2021-10-28
- Completion pending
The Alert Production system (comprising Single Frame Processing, LDM-151 [22] §3.1; Alert Generation, LDM-151 [22] §3.3; and Precovery and Forced Photometry, LDM-151 [22] §3.4) is now available for deployment at the LSST Data Facility. The system is substantially complete, and supports all expected interfaces, data-flows and products, but the details of the algorithms may undergo continued refinement.
DM-AP-17: Moving object processing system (MOPS) available.¶
- WBS: 02C.03
- Level: 3
- Successors: LDM-503-15a, DM-DRP-36
- Due: 2021-12-16
- Completion pending
All of the algorithmic components which comprise the Moving Objects Processing System (MOPS), as described in LDM-151 [22] §§6.25–6.28, are available for integration into science payloads. These components must provide realistic interfaces, data-flows and products, but it is expected that the details of the algorithms will undergo continued refinement.
DM-AP-14: Alert filtering system available.¶
- WBS: 02C.03
- Level: 3
- Predecessors: DM7, F21F, DM-AP-6
- Successors: DM16
- Due: 2022-03-16
- Completion pending
The Alert Filtering Service (LDM-151 [22] §3.3.4; LSE-163 [14] §3.5.2) can now be deployed as part of a prototype Alert Distribution system (LDM-151 [22] §3.3). This service is substantially complete, and supports all expected interfaces, data-flows, and products, but may not yet provide the complete set of filtering capabilities and/or may not perform at the level required to distribute the full LSST alert stream.
02C.04: Data Release Production¶
DLP-588: AFW R&D code refactored¶
- WBS: 02C.04.01
- Level: 3
- Predecessors: LSST-1440
- Due: 2014-08-01
- Completed: 2014-08-01
Warning
No description available
DLP-715: Fundamental centroid and shape measurements¶
- WBS: 02C.04.06
- Level: 3
- Predecessors: LSST-1440
- Due: 2014-08-01
- Completed: 2015-12-04
Warning
No description available
DLP-697: Single epoch CModel minimization¶
- WBS: 02C.04.06
- Level: 3
- Predecessors: LSST-1440
- Due: 2014-08-01
- Completed: 2014-08-01
Warning
No description available
DLP-696: Single epoch Sersic model fitting¶
- WBS: 02C.04.06
- Level: 3
- Predecessors: LSST-1440
- Due: 2014-08-01
- Completed: 2014-08-01
Warning
No description available
DLP-724: Forced per-epoch photometry¶
- WBS: 02C.04.06
- Level: 3
- Due: 2014-09-12
- Completed: 2014-09-12
Warning
No description available
DLP-716: Fundamental flux measurements¶
- WBS: 02C.04.06
- Level: 3
- Due: 2014-09-12
- Completed: 2014-09-12
Warning
No description available
DLP-503: Prototype direct coaddition¶
- WBS: 02C.04.04
- Level: 3
- Due: 2015-08-31
- Completed: 2015-08-31
Warning
No description available
DLP-502: Prototype image artifact identification available¶
- WBS: 02C.04.04
- Level: 3
- Due: 2015-08-31
- Completed: 2015-08-31
Warning
No description available
DLP-101: Prototype coadd detection available¶
- WBS: 02C.04.05
- Level: 3
- Due: 2015-11-24
- Completed: 2016-04-11
Warning
No description available
DLP-73: Footprints redesigned and refactored¶
- WBS: 02C.04.01
- Level: 3
- Due: 2015-11-24
- Completed: 2017-05-09
Warning
No description available
DLP-700: Galaxy shear fitting parameters available¶
- WBS: 02C.04.06
- Level: 3
- Due: 2015-12-04
- Completed: 2016-05-31
Warning
No description available
DLP-288: HSC merger complete¶
- WBS: 02C.04.01
- Level: 3
- Due: 2015-12-29
- Completed: 2016-12-07
Warning
No description available
DLP-486: Prototype merge & deduplication in tract & patch overlaps¶
- WBS: 02C.04.05
- Level: 3
- Successors: DLP-566
- Due: 2016-02-29
- Completed: 2016-04-11
Warning
No description available
DLP-103: Prototype multi-coadd peak association available¶
- WBS: 02C.04.05
- Level: 3
- Successors: DLP-566
- Due: 2016-02-29
- Completed: 2016-04-11
Warning
No description available
DLP-100: Consistent multi-band deblending available¶
- WBS: 02C.04.05
- Level: 3
- Successors: DLP-566
- Due: 2016-02-29
- Completed: 2016-04-11
Warning
No description available
DLP-694: Prototype Brighter-Fatter correction available¶
- WBS: 02C.04.02
- Level: 3
- Successors: DMTC-0000-0020
- Due: 2016-05-31
- Completed: 2016-05-31
Warning
No description available
DM-DRP-1: HSC merger complete: all functionality deployed for the most recent HSC data release processing is now available within the LSST stack.¶
- WBS: 02C.04
- Level: 3
- Successors: DM-NCSA-1, DM-NCSA-16, LDM-503-02
- Due: 2017-05-31
- Completed: 2017-11-01
Warning
No description available
DM-DRP-4: Calibration product generation in support of basic ISR.¶
- WBS: 02C.04
- Level: 3
- Successors: LDM-503-07, DM-AP-7, DM-DRP-20
- Due: 2017-05-31
- Completed: 2017-12-01
Warning
No description available
DLP-736: Performance and capability enhancements in support of catalog use cases¶
- WBS: 02C.04.01
- Level: 3
- Predecessors: DMTC-0000-3000, S17F
- Successors: F17S
- Due: 2017-05-31
- Completed: 2016-12-19
Warning
No description available
DLP-152: Initial PSF-matched image coaddition available¶
- WBS: 02C.04.04
- Level: 3
- Predecessors: S17F
- Due: 2017-05-31
- Completed: 2016-12-19
Warning
No description available
DM-DRP-6: Camera package supporting the Auxiliary Telescope.¶
- WBS: 02C.04
- Level: 3
- Successors: LDM-503-08
- Due: 2017-08-31
- Completed: 2018-01-31
Warning
No description available
DM-DRP-14: Insertion of simulated sources into the data stream to check pipeline performance.¶
- WBS: 02C.04
- Level: 3
- Successors: LDM-503-11b
- Due: 2017-11-30
- Completed: 2017-12-01
Warning
No description available
DM-DRP-18: Initial multi-band deblending algorithm available.¶
- WBS: 02C.04
- Level: 3
- Successors: LDM-503-11b
- Due: 2017-11-30
- Completed: 2017-12-01
Warning
No description available
DM-DRP-16: Global photometric fitting (e.g. Burke et al. Forward Global Calibration Method).¶
- WBS: 02C.04
- Level: 3
- Successors: LDM-503-09a
- Due: 2018-01-31
- Completed: 2018-05-31
Warning
No description available
DM-DRP-32: Object classification system available.¶
- WBS: 02C.04
- Level: 3
- Successors: LDM-503-09a
- Due: 2018-03-30
- Completed: 2018-10-31
Warning
No description available
DM-DRP-3: PSF-homogenized coadd construction.¶
- WBS: 02C.04
- Level: 3
- Predecessors: S18F
- Successors: LDM-503-09a, DM-DRP-37
- Due: 2018-06-29
- Completed: 2017-11-01
Warning
No description available
DM-DRP-5: Camera package supporting the LSST Camera.¶
- WBS: 02C.04
- Level: 3
- Predecessors: S18F
- Successors: LDM-503-09a
- Due: 2018-06-29
- Completed: 2018-06-29
Warning
No description available
DM-DRP-38: Camera package supporting the Commissioning Camera.¶
- WBS: 02C.04
- Level: 3
- Predecessors: S18F
- Successors: LSST-1513, LDM-503-09a
- Due: 2018-06-29
- Completed: 2018-06-29
Warning
No description available
DM-DRP-7: Coordinate transformation tool provided for use with the Collimated Beam Projector.¶
- WBS: 02C.04
- Level: 3
- Successors: LDM-503-09a, T&SC-2100-2252
- Due: 2018-07-12
- Completed: 2018-07-05
Warning
No description available
DM-DRP-17: Simultaneous photometric and astrometric fitting to multiple exposures.¶
- WBS: 02C.04
- Level: 3
- Predecessors: S18F, DM-AP-9
- Successors: LDM-503-09a
- Due: 2018-07-20
- Completed: 2018-11-29
Warning
No description available
DM-DRP-9: Data reduction pipeline for the Auxiliary Telescope.¶
- WBS: 02C.04
- Level: 3
- Predecessors: S18F
- Successors: LDM-503-11b, DM-DRP-23
- Due: 2018-10-15
- Completed: 2019-03-25
Warning
No description available
DM-DRP-19: QA metrics are generated during pipeline execution.¶
- WBS: 02C.04
- Level: 3
- Predecessors: S18F
- Successors: LDM-503-11b
- Due: 2018-11-29
- Completed: 2018-12-13
Warning
No description available
DM-DRP-2: Basic visualization and quality assessment tools operational on HSC-scale data volumes.¶
- WBS: 02C.04
- Level: 3
- Predecessors: DM-NCSA-3, DM-DAX-5
- Successors: LDM-503-02
- Due: 2019-02-28
- Completed: 2017-11-01
Warning
No description available
DM-DRP-11: Pipelines code provides supports for database ingestion of results.¶
- WBS: 02C.04
- Level: 3
- Predecessors: S18F
- Successors: F20F, DM-DAX-5
- Due: 2019-02-28
- Completed: 2019-12-31
The Data Release Production science payload now generates results which are compliant with the LSST Science Data Model, and which are suitable for database ingest.
DM-DRP-12: Background estimation over the full visit.¶
- WBS: 02C.04
- Level: 3
- Predecessors: DM-DAX-8
- Successors: LSST-1580
- Due: 2020-11-30
- Completed: 2020-06-30
Warning
No description available
DM-DRP-15: All varieties of coadd required for object detection and characterization are now produced during normal pipeline operation (although not necessarily at the ultimately required level of fidelity).¶
- WBS: 02C.04
- Level: 3
- Predecessors: DM-DAX-9
- Successors: LDM-503-11b
- Due: 2020-11-30
- Completed: 2018-11-30
Warning
No description available
DM-DRP-8: Calibration product generation for the Auxiliary Telescope.¶
- WBS: 02C.04
- Level: 3
- Predecessors: S18F, COMC-060200-10000
- Successors: LSST-1580
- Due: 2020-12-01
- Completion pending
The Calibration Products Production science payload is now capable of generating those products which are required to calibrate the Auxiliary Telescope. This represent an initial capability, providing realistic interfaces, data-flows and products; ongoing refinement of the algorithms being used is expected.
DM-DRP-13: PSF estimation over the full visit.¶
- WBS: 02C.04
- Level: 3
- Predecessors: DM-DAX-8
- Successors: LSST-1580
- Due: 2020-12-01
- Completion pending
The Data Release Production science payload now includes code for estimating the PSF over the full focal plane, as described in LDM-151 [22] §6.11.3. This does not require that the PSF model be “physically motivated” (ie, decomposed into atmospheric and optical components). Further, this represents an initial capability, providing realistic interfaces, data-flows and products; ongoing refinement of the algorithm being used is expected.
DM-DRP-37: Artifact rejection and background matching during coadd construction.¶
- WBS: 02C.04
- Level: 3
- Predecessors: F18F, DM-DRP-3
- Successors: LSST-1580
- Due: 2020-12-01
- Completion pending
The Data Release Production science payload now includes code for generating final estimates of the sky background and artifact masks, as described in LDM-151 [22] §5.2.2. This represents an initial capability, providing realistic interfaces, data-flows and products; ongoing refinement of the algorithm being used is expected.
DM-DRP-22: Template generation integrated with Data Release Production pipelines.¶
- WBS: 02C.04
- Level: 3
- Predecessors: F20S
- Successors: LDM-503-13a
- Due: 2020-12-01
- Completion pending
The Data Release Production science payload is now capable of generating templates for use in image differencing, as described in LDM-151 [22] §§5.2.3 & 5.2.4. This represents an initial capability, providing realistic interfaces, data-flows and products; ongoing refinement of the algorithm being used is expected.
DM-DRP-24: Physically motivated PSF model, including separate characterization of contributions from the atmosphere and the telescope system.¶
- WBS: 02C.04
- Level: 3
- Predecessors: F20S
- Successors: LSST-1580
- Due: 2020-12-01
- Completion pending
Per LDM-151 [22] §6.11.3, the PSF model used by the Data Release Production science payload is now decomposed into separate contributions from the telescope optics and the atmosphere.
DM-DRP-29: Moving point source model fitting now available.¶
- WBS: 02C.04
- Level: 3
- Predecessors: F18F
- Successors: LSST-1580
- Due: 2020-12-01
- Completion pending
The Data Release Production science payload now includes the capability of fitting moving a moving point source model that includes parallax and proper motion as free parameters to all objects, as described in LDM-151 [22] §6.7.2. This represents an initial capability, providing realistic interfaces, data-flows and products; ongoing refinement of the algorithms being used is expected.
DM-DRP-35: Simultaneous measurement across a suite of coadds representing different bandpasses, epocs, and flavors.¶
- WBS: 02C.04
- Level: 3
- Successors: DM-DRP-31
- Due: 2021-02-23
- Completion pending
The Data Release Production science payload now includes the capability to perform consistent measurement of all Objects in a patch across multiple coadds, as described in LDM-151 [22] §5.3.4. This represents an initial capability, providing realistic interfaces, data-flows and products; ongoing refinement of the algorithms being used is expected.
DM-DRP-26: Overlap resolution at tract & patch boundaries.¶
- WBS: 02C.04
- Level: 3
- Predecessors: DM-DRP-27
- Successors: LDM-503-13a
- Due: 2021-04-28
- Completion pending
The Data Release Production science payload is now capable of finalizing the definition of Objects which fall within the overlap regions at the edges of tracts and patches, as described in LDM-151 [22] §5.4. This represents an initial capability, providing realistic interfaces, data-flows and products; ongoing refinement of the algorithm being used is expected.
DM-DRP-27: Object generation: association and assembly of (DIA, coadd, etc) sources to form objects.¶
- WBS: 02C.04
- Level: 3
- Predecessors: DM-DRP-28
- Successors: LDM-503-13a, DM-DRP-26
- Due: 2021-04-28
- Completion pending
The Data Release Production science payload now includes the capability to build Objects by cross-matching the Source and DIASource tables, as described in LDM-151 [22] §5.3.2. This represents an initial capability, providing realistic interfaces, data-flows and products; ongoing refinement of the algorithm being used is expected.
DM-DRP-28: Difference images are now a first-class data product during data release processing.¶
- WBS: 02C.04
- Level: 3
- Predecessors: DM-AP-11
- Successors: LDM-503-13a, DM-DRP-27
- Due: 2021-04-28
- Completion pending
The Data Release Production science payload now includes the capability to generate difference images, and to perform source detection and characterization on those images, as described in LDM-151 [22] §5.2.5. This represents an initial capability, providing realistic interfaces, data-flows and products; ongoing refinement of the algorithm being used is expected.
DM-DRP-21: Integrated image characterization pipeline for Data Release Production.¶
- WBS: 02C.04
- Level: 3
- Predecessors: DM-AP-9, DM-DAX-8, DM-DAX-9
- Successors: LSST-1580
- Due: 2021-06-02
- Completion pending
The Data Release Production science payload now includes an integrated image characterization pipeline, as described in LDM-151 [22] §5.1, including iterative refinement of the image characterization. This represents an initial capability, providing realistic interfaces, data-flows and products; ongoing refinement of the algorithm being used is expected.
DM-DRP-30: Forced photometry is now performed on individual processed visit images during data releases.¶
- WBS: 02C.04
- Level: 3
- Predecessors: F20F
- Successors: LDM-503-13a
- Due: 2021-06-02
- Completion pending
The Data Release Production science payload now includes the capability of performing “forced” photometry at the positions of known Objects on Processed Visit Images, as described in LDM-151 [22] §5.5.2. This represents an initial capability, providing realistic interfaces, data-flows and products; ongoing refinement of the algorithm being used is expected.
DM-DRP-25: Prototype multi-epoch fitting system available.¶
- WBS: 02C.04
- Level: 3
- Predecessors: F20F, DM-DAX-10
- Successors: DM7, LDM-503-13a
- Due: 2021-06-02
- Completion pending
A prototype of the “MultiFit” multi-epoch fitting is now available for testing. This provides the capabilities described in LDM-151 [22] §5.5.1, but it is not necessarily integrated with the Data Release Production science payload (i.e., it may not be run in regular dataset reprocessing, and it may require separate/additional scripts or ancillary artifacts).
DM-DRP-34: Selection maps are generated during data releases.¶
- WBS: 02C.04
- Level: 3
- Predecessors: F20F
- Successors: LDM-503-13a
- Due: 2021-06-02
- Completion pending
The Data Release Production science payload now includes the capability of generating multi-scale maps that describe LSST’s depth and efficiency at detecting different classes of object as part of a data release, as described in LDM-151 [22] §5.6.3. This represents an initial capability, providing realistic interfaces, data-flows and products; ongoing refinement of the algorithms being used is expected.
DM-DRP-31: A photometric redshift is now provided for each object.¶
- WBS: 02C.04
- Level: 3
- Predecessors: DM-DRP-35
- Successors: DM-DRP-36
- Due: 2021-08-30
- Completion pending
The Data Release Production science payload now includes the capability of calculating photometric redshifts as part of a data release, as (briefly) described in LDM-151 [22] §5.6.5. This represents an initial capability, providing realistic interfaces, data-flows and products; ongoing refinement of the algorithm being used is expected.
DM-DRP-23: Atmospheric characterization based on data from the Auxiliary Telescope now available.¶
- WBS: 02C.04
- Level: 3
- Predecessors: F21S, DM-DRP-9, COMC-060200-10000
- Successors: LSST-1580
- Due: 2021-08-31
- Completion pending
The Calibration Products Production science payload is now capable of producing an atmospheric transmission model based on observations from the Auxiliary Telescope, as described in LDM-151 [22] §4.6.1. This milestone does not presume that the Auxiliary Telescope itself is available for testing: it is satisfied by the availability of a pipeline that can process appropriate simulated or precursor data. This represents an initial capability, providing realistic interfaces, data-flows and products; ongoing refinement of the algorithm being used is expected.
DM-DRP-36: MOPS integrated to data release processing.¶
- WBS: 02C.04
- Level: 3
- Predecessors: DM-AP-17, DM-DRP-31
- Successors: LSST-1580
- Due: 2021-12-16
- Completion pending
The Data Release Production science payload now generates SSObjects, by delegating to the Moving Objects Processing System (MOPS) being delivered by the Alert Production team, as described in LDM-151 [22] §5.6.1. This represents an initial capability, providing realistic interfaces, data-flows and products; ongoing refinement of the algorithm being used is expected.
DM-DRP-20: Refined set of LSST calibration products.¶
- WBS: 02C.04
- Level: 3
- Predecessors: DM-DRP-4, COMC-0100
- Successors: LSST-1580
- Due: 2022-03-14
- Completion pending
The Calibration Products Production science payload is now capable of generating all calibration products which are required to enter commissioning.
02C.05: Science User Interface and Tools¶
DLP-578: Propose a workspace structure for discussion.¶
- WBS: 02C.05.05
- Level: 3
- Predecessors: LSST-1440
- Due: 2014-08-01
- Completed: 2014-08-01
Warning
No description available
DLP-574: Evaluate best-of-breed tools. Technology exploration.¶
- WBS: 02C.05.01
- Level: 3
- Predecessors: LSST-1440
- Due: 2014-08-01
- Completed: 2014-08-01
Warning
No description available
DLP-575: Evaluate best-of-breed tools. Technology exploration.¶
- WBS: 02C.05.02
- Level: 3
- Predecessors: LSST-1440
- Due: 2014-08-01
- Completed: 2014-08-01
Warning
No description available
DLP-576: Evaluate best-of-breed tools. Technology exploration.¶
- WBS: 02C.05.03
- Level: 3
- Predecessors: LSST-1440
- Due: 2014-08-01
- Completed: 2014-08-01
Warning
No description available
DLP-577: Evaluate best-of-breed tools. Technology exploration.¶
- WBS: 02C.05.04
- Level: 3
- Predecessors: LSST-1440
- Due: 2014-08-01
- Completed: 2014-08-01
Warning
No description available
DLP-519: Research the development framework for SUI¶
- WBS: 02C.05.01
- Level: 3
- Due: 2014-10-14
- Completed: 2014-10-14
Warning
No description available
DLP-520: Access Qserv for catalog search in SUI prototype¶
- WBS: 02C.05.01
- Level: 3
- Due: 2014-12-02
- Completed: 2014-12-02
Warning
No description available
DLP-521: Define the data access APIs with database team¶
- WBS: 02C.05.01
- Level: 3
- Due: 2015-03-11
- Completed: 2015-03-11
Warning
No description available
DLP-518: Evaluate best-of-breed tools. Technology exploration.¶
- WBS: 02C.05.05
- Level: 3
- Due: 2015-03-20
- Completed: 2015-03-20
Warning
No description available
DLP-564: Able to use some data-access APIs developed by database team¶
- WBS: 02C.05.01
- Level: 3
- Due: 2015-07-28
- Completed: 2015-11-17
Warning
No description available
DLP-256: First draft definition of workspace¶
- WBS: 02C.05.05
- Level: 3
- Due: 2015-07-31
- Completed: 2015-11-17
Warning
No description available
DLP-218: Provide API for image display in Firefly¶
- WBS: 02C.05.02
- Level: 3
- Due: 2015-08-31
- Completed: 2015-11-17
Warning
No description available
DLP-216: Provide basic APIs to use Firefly visualization components¶
- WBS: 02C.05.02
- Level: 3
- Due: 2015-08-31
- Completed: 2016-11-02
Warning
No description available
DLP-872: Convert major portion of GWT in Firefly to pure JavaScript¶
- WBS: 02C.05.01
- Level: 3
- Due: 2016-02-24
- Completed: 2016-04-08
Warning
No description available
DM-SUIT-3: Time series analysis tool for WISE data¶
- WBS: 02C.05
- Level: 3
- Successors: LDM-503-01
- Due: 2016-09-30
- Completed: 2017-11-30
Warning
No description available
DLP-871: Firefly server side code refactor¶
- WBS: 02C.05.01
- Level: 3
- Predecessors: DMTC-0000-0030
- Successors: S17S
- Due: 2016-11-30
- Completed: 2017-07-31
Warning
No description available
DM-SUIT-2: Search WISE coaded data single exposure images in PDAC (the images are from IRSA at IPAC, not NCSA)¶
- WBS: 02C.05
- Level: 3
- Predecessors: DM-DAX-2
- Successors: LDM-503-01
- Due: 2017-07-31
- Completed: 2017-11-30
Warning
No description available
DM-SUIT-1: Search and display WISE sources (objects) in PDAC¶
- WBS: 02C.05
- Level: 3
- Predecessors: DM-DAX-1
- Successors: LDM-503-01
- Due: 2017-11-30
- Completed: 2017-11-30
Warning
No description available
DM-SUIT-4: Multiple data traces in chart space¶
- WBS: 02C.05
- Level: 3
- Successors: LDM-503-01
- Due: 2017-11-30
- Completed: 2017-11-30
Warning
No description available
DLP-207: Extra LSST query capabilities in web UI¶
Warning
No description available
DLP-205: LSST web UI search external catalog¶
Warning
No description available
DLP-222: Provide time-domain data view¶
Warning
No description available
DM-SUIT-8: SUIT portal integrated with workspace¶
- WBS: 02C.05
- Level: 3
- Successors: DM-SUIT-10
- Due: 2018-11-30
- Completed: 2020-05-29
Portal is integrated with LSST-provided WebDAV or VOSpace service exposing the User File Workspace. Portal provides functions for saving image and catalog query results to the logged-in user’s workspace, with the user’s identity correctly applied. Portal provides functions for accessing data in the user’s workspace and displaying it using the Portal’s image and table visualization tools, as well as using data from the workspace in other Portal contexts where a file can be uploaded, e.g., to perform a multi-object query. (NB: Still achievable post-DM-10, though only with WebDAV.).
DM-SUIT-7: Mapping between SUIT systems & NCSA auth system¶
- WBS: 02C.05
- Level: 3
- Predecessors: S19F
- Successors: DM-SUIT-10
- Due: 2019-05-31
- Completed: 2019-05-31
Portal is integrated with NCSA-provided federated-identity authentication and authorization system: the Portal recognizes that a user is logged in and displays that state, and passes the user’s identity along to LSST data services that it accesses. (NB: Still achievable post-DM-10) Claimed in May, based on installation on lsst-lsp-int.
DM-SUIT-10: SUIT deployment procedure¶
- WBS: 02C.05
- Level: 3
- Predecessors: S19F, DM-SUIT-7, DM-SUIT-8
- Successors: LDM-503-11a
- Due: 2019-05-31
- Completed: 2020-06-30
Portal software is adapted for deployment in Kubernetes. The set of container images required for deployment is documented in an LTD-style manner. Configuration files for Kubernetes are provided in Github and documented to a level that permits deployments to be performed by non-IPAC staff. (NB: Still achievable post-DM-10).
DM-SUIT-5: Search and display processed HSC data¶
- WBS: 02C.05
- Level: 3
- Predecessors: DM-NCSA-2, DM-NCSA-3, DM-DAX-2, DM-DAX-5
- Successors: LDM-503-09
- Due: 2020-12-01
- Completion pending
Portal provides access to a collection of public-release HSC data processed by LSST DM, including calibrated single-epoch images, coadds, and catalogs (including at least an Object-like catalog). Access is obtained via IVOA interfaces including TAP for catalogs and ObsTAP for image metadata. (NB: Still achievable post-DM-10).
02C.06: Science Data Archive and Application Services¶
DLP-836: New logging for DM¶
- WBS: 02C.06.02
- Level: 3
- Predecessors: LSST-1440
- Due: 2014-08-01
- Completed: 2015-11-17
Warning
No description available
DLP-835: New xrootd client¶
- WBS: 02C.06.02
- Level: 3
- Predecessors: DLP-834
- Due: 2014-08-01
- Completed: 2014-08-01
Warning
No description available
DLP-834: Automated Testbed for Qserv¶
- WBS: 02C.06.02
- Level: 3
- Predecessors: LSST-1440
- Successors: DLP-835
- Due: 2014-08-01
- Completed: 2014-08-01
Warning
No description available
DLP-818: CSS¶
- WBS: 02C.06.02
- Level: 3
- Due: 2014-11-25
- Completed: 2015-11-17
Warning
No description available
DLP-801: Qserv uses C++-based Geometry Code¶
- WBS: 02C.06.02
- Level: 3
- Due: 2014-11-25
- Completed: 2015-11-17
Warning
No description available
DLP-817: Multi-node Multi-query Integration Testing Harness¶
- WBS: 02C.06.02
- Level: 3
- Due: 2015-05-29
- Completed: 2015-11-17
Warning
No description available
DLP-800: Data Ingest into MySQL¶
- WBS: 02C.06.01
- Level: 3
- Due: 2015-05-29
- Completed: 2015-11-17
Warning
No description available
DLP-25: Prototype Web Service for SUI¶
- WBS: 02C.06.02
- Level: 3
- Due: 2015-08-31
- Completed: 2015-09-01
Warning
No description available
DLP-805: Distributed Database and Table Management¶
- WBS: 02C.06.02
- Level: 3
- Due: 2015-10-29
- Completed: 2015-10-29
Warning
No description available
DLP-635: Qserv Query Cancellation¶
- WBS: 02C.06.02
- Level: 3
- Due: 2015-11-25
- Completed: 2016-01-12
Warning
No description available
DLP-472: Qserv Data Distribution¶
- WBS: 02C.06.02
- Level: 3
- Predecessors: DMTC-0000-3000, S17F
- Due: 2017-05-31
- Completed: 2018-06-29
Warning
No description available
DM-DAX-2: Query service supporting IVOA TAP protocol, w/ support for asynchronous queries¶
- WBS: 02C.06
- Level: 3
- Successors: LDM-503-09, LDM-503-10a, DM-SUIT-2, DM-SUIT-5
- Due: 2017-07-31
- Completed: 2019-11-29
An IVOA TAP service supporting both synchronous and asynchronous query models, integrated with the LSP authentication architecture, and able to access catalog data hosted in a downstream in Qserv instance.
DM-DAX-1: WISE data ingest to PDAC¶
- WBS: 02C.06
- Level: 3
- Successors: LDM-503-01, DM-SUIT-1
- Due: 2017-11-30
- Completed: 2017-11-01
Warning
No description available
DM-DAX-6: Prototype level 1 database¶
- WBS: 02C.06
- Level: 3
- Successors: DM-NCSA-9, LDM-503-03
- Due: 2017-11-30
- Completed: 2017-11-01
Warning
No description available
DLP-473: Async Queries in Qserv¶
- WBS: 02C.06.02
- Level: 3
- Predecessors: S17F, F17F
- Successors: DLP-725
- Due: 2017-11-30
- Completed: 2017-11-01
Warning
No description available
DLP-725: Working Prototype of AP/L1 Database¶
- WBS: 02C.06.01
- Level: 3
- Predecessors: F17F, DLP-473
- Successors: S18S
- Due: 2017-11-30
- Completed: 2017-11-01
Warning
No description available
DLP-837: AP-ready Butler Framework¶
- WBS: 02C.06.02
- Level: 3
- Successors: F20F
- Due: 2017-12-01
- Completed: 2019-08-30
Warning
No description available
DM-DAX-11: Transformed EFD schema¶
- WBS: 02C.06
- Level: 3
- Successors: LSST-1580
- Due: 2018-03-30
- Completed: 2018-05-31
Warning
No description available
DM-DAX-10: Per-object gather support in Butler¶
Demonstrate Butler configuration able to gather all data pertaining to a particular object, such as retrieving cutous from all warps at a given bbox on a skymap.
DM-DAX-7: Generation 3 Butler, running on a POSIX file-system provided by NCSA¶
- WBS: 02C.06
- Level: 3
- Predecessors: DM-DAX-12
- Due: 2020-11-30
- Completed: 2020-06-30
Given a stood-up data backbone instance, demonstrate instantiation/configuration of a Butler Gen3 instance capable of retrieving images from that backbone instance. (As currently conceived, the data backbone is either a GPFS filesystem or object store, in combination with metadata that is a superset of that maintained in a Butler Gen3 registry. Depending on particular technologies and implementation strategies chosen for the data backbone, this may be either a “simple matter of configuration” of existing Butler connectors, or may require some additional custom connectors to be written.).
DM-DAX-8: Scatter-gather support in PipelineTask¶
- WBS: 02C.06
- Level: 3
- Predecessors: F18F, DM-DAX-12
- Successors: DM-DRP-12, DM-DRP-13, DM-DRP-21
- Due: 2020-11-30
- Completed: 2020-06-30
Demonstrate a functional PipelineTask with scatter/gather functionality, such as Jointcal, SkyCorrect, or FGCM.
DM-DAX-5: Database ingest in support of HSC reprocessing (ie, large catalog ingest)¶
- WBS: 02C.06
- Level: 3
- Predecessors: DM-DRP-11
- Successors: DM-NCSA-3, LDM-503-09, DM-SUIT-5, DM-DRP-2
- Due: 2020-12-01
- Completion pending
Existing Qserv ingest tooling is highly manual and poorly parallellized. Develop new tooling to address these issues and support ingest campaigns at the scale needed for DRP.
DLP-802: Alert Production Database (APDB) design¶
- WBS: 02C.06.01
- Level: 3
- Due: 2020-12-01
- Completion pending
Warning
No description available
DM-DAX-9: Provenance system¶
- WBS: 02C.06
- Level: 3
- Predecessors: F18F, DM-DAX-12, DM-DAX-14
- Successors: LDM-503-09, DM-DRP-15, DM-DRP-21
- Due: 2021-06-02
- Completion pending
Warning
No description available
DM-DAX-12: Generation 3 middleware at feature parity with Generation 2¶
- WBS: 02C.06
- Level: 3
- Predecessors: F20F
- Successors: DM-NCSA-15, DM-NCSA-22, DM-DAX-7, DM-DAX-8, DM-DAX-9, DM-DAX-13
- Due: 2021-06-02
- Completion pending
Generation 3 middleware, consisting of Butler updates and the PipelineTask framework, are now able to support existing science payloads with no loss of functionality over previous versions. That is, Gen 3 may not be feature complete, but Gen 2 can be retired with no functionality regressions across the subsystem.
DM-DAX-14: Provenance system review completed¶
Warning
No description available
DM-DAX-13: Generation 2 middleware retired¶
- WBS: 02C.06
- Level: 3
- Predecessors: S21F, DM-DAX-12
- Successors: LSST-1580
- Due: 2021-08-30
- Completion pending
The Generation 2 middleware is deprecated, and may be removed from the codebase. No current science payload and no current execution service makes use of it.
02C.07: LSST Data Facility¶
DLP-359: Improve fault tolerance in AP simulator¶
- WBS: 02C.07.01
- Level: 3
- Due: 2014-11-19
- Completed: 2014-11-19
Warning
No description available
DLP-360: Prepare for OCS Middleware integration with AP DMCS¶
- WBS: 02C.07.01
- Level: 3
- Due: 2014-11-21
- Completed: 2014-11-21
Warning
No description available
DLP-422: Evaluate OpenStack as a development environment¶
- WBS: 02C.07.03
- Level: 3
- Due: 2015-01-29
- Completed: 2015-01-29
Warning
No description available
DLP-450: Support lsst-dev for developers¶
- WBS: 02C.07.04
- Level: 3
- Due: 2015-02-02
- Completed: 2015-02-02
Warning
No description available
DLP-449: Upgrade storage server hardware¶
- WBS: 02C.07.04
- Level: 3
- Due: 2015-02-02
- Completed: 2016-07-15
Warning
No description available
DLP-400: Refactor basic event services¶
- WBS: 02C.07.02
- Level: 3
- Successors: DLP-556
- Due: 2015-05-28
- Completed: 2015-01-26
Warning
No description available
DLP-441: Base Center requirements document¶
- WBS: 02C.07.04
- Level: 3
- Due: 2015-05-29
- Completed: 2015-05-29
Warning
No description available
DLP-451: Deploy OpenStack capability¶
- WBS: 02C.07.04
- Level: 3
- Due: 2015-07-30
- Completed: 2015-07-30
Warning
No description available
DLP-356: Set up Joint Coordination Council (JCC) for coordination with satellite processing center¶
- WBS: 02C.07.00
- Level: 3
- Due: 2015-08-26
- Completed: 2015-08-26
Warning
No description available
DLP-361: Build prototype AP DMCS, including events¶
- WBS: 02C.07.01
- Level: 3
- Due: 2015-08-26
- Completed: 2015-08-26
Warning
No description available
DLP-355: Establish MOA with CC-IN2P3 satellite processing center¶
- WBS: 02C.07.00
- Level: 3
- Due: 2015-08-31
- Completed: 2015-08-31
Warning
No description available
DLP-404: Identify candidate security packages¶
- WBS: 02C.07.02
- Level: 3
- Due: 2015-08-31
- Completed: 2016-06-07
Warning
No description available
DLP-410: Implement Puppet for system configuration management¶
- WBS: 02C.07.02
- Level: 3
- Due: 2015-08-31
- Completed: 2015-08-31
Warning
No description available
DLP-415: Evaluate iRODS, Datacat, and similar file system management technologies¶
- WBS: 02C.07.02
- Level: 3
- Due: 2015-08-31
- Completed: 2015-08-31
Warning
No description available
DLP-423: DevOps assessment¶
- WBS: 02C.07.03
- Level: 3
- Due: 2015-08-31
- Completed: 2015-08-31
Warning
No description available
DLP-430: Initial refinement of facility integration plan¶
- WBS: 02C.07.04
- Level: 3
- Due: 2015-08-31
- Completed: 2015-08-31
Warning
No description available
DLP-357: Initial refinement of facility integration plan¶
- WBS: 02C.07.01
- Level: 3
- Successors: DLP-358
- Due: 2015-09-29
- Completed: 2016-06-15
Warning
No description available
DLP-389: Implement advanced logging functionality, including event-based logging¶
- WBS: 02C.07.01
- Level: 3
- Successors: DLP-566
- Due: 2015-09-29
- Completed: 2015-09-29
Warning
No description available
DLP-452: Support datasets on basic file system infrastructure with apropos policies¶
- WBS: 02C.07.04
- Level: 3
- Due: 2016-01-22
- Completed: 2016-07-15
Warning
No description available
DLP-411: Monitor OpenStack¶
- WBS: 02C.07.02
- Level: 3
- Successors: DLP-412
- Due: 2016-02-05
- Completed: 2016-06-07
Warning
No description available
DLP-850: Prototype authentication/authorization system complete¶
- WBS: 02C.07.02
- Level: 3
- Successors: S17S
- Due: 2016-02-22
- Completed: 2016-06-07
Warning
No description available
DLP-405: Investigate CAS integration with Internet2 AAA tools¶
- WBS: 02C.07.02
- Level: 3
- Successors: S17S
- Due: 2016-02-22
- Completed: 2016-07-15
Warning
No description available
DLP-469: Coordination with NCSA/CC-IN2P3 JCC¶
- WBS: 02C.07.00
- Level: 3
- Successors: DLP-864
- Due: 2016-02-24
- Completed: 2016-06-07
Warning
No description available
DLP-358: Refinement of facility integration plan and traceability of science and operational requirements¶
- WBS: 02C.07.01
- Level: 3
- Predecessors: DLP-357
- Due: 2016-02-24
- Completed: 2016-04-08
Warning
No description available
DLP-364: Build prototype production sequence for the DMCS¶
- WBS: 02C.07.01
- Level: 3
- Successors: DLP-566
- Due: 2016-02-24
- Completed: 2016-06-07
Warning
No description available
DLP-471: Refresh sizing model¶
- WBS: 02C.07.04
- Level: 3
- Due: 2016-02-24
- Completed: 2016-06-07
Warning
No description available
DLP-431: Refinement of facility integration plan and traceability of science and operational requirements¶
- WBS: 02C.07.04
- Level: 3
- Due: 2016-02-24
- Completed: 2016-07-15
Warning
No description available
DLP-424: Integration of DevOps to OpenStack¶
- WBS: 02C.07.03
- Level: 3
- Due: 2016-02-29
- Completed: 2016-07-15
Warning
No description available
DLP-847: Meet camera DAQ/OCS milestones for FY16¶
- WBS: 02C.07.01
- Level: 3
- Predecessors: DMTC-0000-0030
- Successors: F17F
- Due: 2016-11-30
- Completed: 2017-09-01
Warning
No description available
DLP-366: Mid-scale processing of eligible camera data¶
- WBS: 02C.07.01
- Level: 3
- Predecessors: DMTC-0000-0030
- Successors: F17F
- Due: 2016-11-30
- Completed: 2017-11-01
Warning
No description available
DLP-412: Monitor development cluster¶
- WBS: 02C.07.02
- Level: 3
- Predecessors: DLP-411, DMTC-0000-0030
- Successors: S18S
- Due: 2016-11-30
- Completed: 2017-09-01
Warning
No description available
DM-NCSA-1: Provide regular reprocessing service for HSC data¶
- WBS: 02C.07
- Level: 3
- Predecessors: DM-DRP-1
- Successors: DM-NCSA-2, LDM-503-02
- Due: 2017-05-31
- Completed: 2017-11-01
Warning
No description available
DM-NCSA-2: Provide access to results of regular reprocessing (NB the form this takes depends upon available DAX functionality)¶
- WBS: 02C.07
- Level: 3
- Predecessors: DM-NCSA-1
- Successors: LDM-503-02, DM-SUIT-5
- Due: 2017-05-31
- Completed: 2017-11-01
Warning
No description available
DM-NCSA-28: IIP control code¶
- WBS: 02C.07
- Level: 3
- Successors: DM-NCSA-29, LSST-1190
- Due: 2017-09-29
- Completed: 2017-11-01
Warning
No description available
DLP-864: Coordination with NCSA/CC-IN2P3 JCC¶
- WBS: 02C.07.00
- Level: 3
- Predecessors: DLP-469
- Successors: S18F
- Due: 2017-11-30
- Completed: 2017-11-01
Warning
No description available
DLP-368: Initial AP DMCS¶
Warning
No description available
DLP-459: Qserv capability to hold data reduced at NCSA¶
Warning
No description available
DLP-458: Ingest of bulk data from real cameras to ComCam scale¶
Warning
No description available
DLP-457: Support runs on real cameras data and ImSim data¶
Warning
No description available
DLP-442: Procure infrastructure for Base Center to meet FY18 goals¶
- WBS: 02C.07.04
- Level: 3
- Predecessors: F17F
- Due: 2017-11-30
- Completed: 2018-04-30
Warning
No description available
DLP-433: Procure infrastructure for Archive Center to FY18 scale¶
- WBS: 02C.07.04
- Level: 3
- Predecessors: F17F
- Due: 2017-11-30
- Completed: 2018-04-30
Warning
No description available
DMTC-4500-0010: Start NCSA S18¶
- WBS: 02C.07
- Level: 3
- Due: 2017-12-01
- Completed: 2017-12-01
Time-based milestone marking the start of NCSA’s Spring 2018 development cycle.
DM-NCSA-27: Deliver header service code¶
- WBS: 02C.07
- Level: 3
- Successors: LDM-503-04b, LSST-1160
- Due: 2017-12-29
- Completed: 2017-12-01
Warning
No description available
DM-NCSA-29: Deliver IIP image client code¶
- WBS: 02C.07
- Level: 3
- Predecessors: DM-NCSA-28
- Successors: LSST-1200
- Due: 2017-12-29
- Completed: 2018-03-31
Warning
No description available
DM-NCSA-6: Ability to transfer files originating from Tucson to NCSA and ingest files at NCSA, including metadata and provenance¶
- WBS: 02C.07
- Level: 3
- Successors: LDM-503-04b
- Due: 2018-03-05
- Completed: 2018-10-31
Warning
No description available
DM-NCSA-5: Level 1 archiving system able to acquire pixel data from the Aux Tel DAQ, header metadata via OCS, assemble FITS image,¶
- WBS: 02C.07
- Level: 3
- Successors: LDM-503-04b
- Due: 2018-03-30
- Completed: 2018-05-31
Warning
No description available
DM-NCSA-7: Capability to paint displays for Tucson and NCSA¶
- WBS: 02C.07
- Level: 3
- Successors: LDM-503-04b
- Due: 2018-03-30
- Completed: 2018-06-29
Warning
No description available
DM-NCSA-9: Test instance of alert distribution hosting service and L1 database in Development & Integration Enclave¶
- WBS: 02C.07
- Level: 3
- Predecessors: DM-DAX-6
- Successors: LDM-503-05, DM-AP-6
- Due: 2018-08-31
- Completed: 2019-05-31
Hosting an instance of the alert distribution service delivered from University of Washington on our test containerized application management service platform, running feeds from the pipeline to the distribution services. Note: This was informally tied to LDM-503-05, which was de-scoped to a small demonstration of running an instance of Kafka at NCSA, so no L1 database was needed. We believe this was completed in August 2018.
DM-NCSA-10: Sustained archiving service that is OCS commandable¶
- WBS: 02C.07
- Level: 3
- Successors: LDM-503-06
- Due: 2018-09-25
- Completed: 2019-05-31
The capability to use the existing OCS/CCS to command data acquisition and hand-off to a test Observatory Operations Data Service (OODS).
DM-NCSA-3: Provide database for metadata, provenance, location and demonstrate ingest at small scale¶
- WBS: 02C.07
- Level: 3
- Predecessors: DM-DAX-5
- Successors: DM-NCSA-4, LDM-503-02, DM-SUIT-5, DM-DRP-2
- Due: 2019-02-28
- Completed: 2017-11-01
Warning
No description available
DM-NCSA-4: Minimal support for the small operational schema including file metadata and provenance for every file, and record of in¶
- WBS: 02C.07
- Level: 3
- Predecessors: DM-NCSA-3, LDM-503-02
- Successors: LDM-503-04
- Due: 2019-02-28
- Completed: 2018-06-29
Warning
No description available
DM-NCSA-16: Perform ISR processing on ComCam-scale data.¶
- WBS: 02C.07
- Level: 3
- Predecessors: DM-DRP-1
- Successors: LDM-503-09, LDM-503-11, LDM-503-11a
- Due: 2019-03-29
- Completed: 2019-06-13
Process ComCam-scale data through the ISR pipeline to generate QC parameters used by the observatory.
A5090: Expected Arrival of ComCam Systems to NCSA¶
- WBS: 02C.07.09
- Level: 4
- Predecessors: T&SC-6500-8100
- Due: 2019-05-08
- Completed: 2019-04-30
Arrival at NCSA of hardware to support ComCam testing and integration.
DM-NCSA-13: Header Writing Service for Spectrograph use case¶
- WBS: 02C.07
- Level: 3
- Successors: LDM-503-08
- Due: 2019-05-14
- Completed: 2019-05-31
The Header builder integrated into OCS and demonstrated. Header builder has identified sources of information for all modes of observing with the Spectrograph.
A4640: Ship ComCam Hardware to Tucson¶
- WBS: 02C.07.09
- Level: 4
- Due: 2019-06-20
- Completed: 2019-06-27
Date for ComCam support systems to ship from NCSA to Tucson.
A2330: Ship AA System to Chile¶
- WBS: 02C.07.09
- Level: 4
- Due: 2019-06-28
- Completed: 2019-06-28
Date for Authenticaton and Authorization hardware to ship from NCSA to Chile.
A4369.9: Ship Hardware to BDC¶
- WBS: 02C.07.09
- Level: 4
- Successors: A4670
- Due: 2019-07-15
- Completed: 2019-07-17
Date for Base Data Center hardware to ship from NCSA to Chile.
DM-NCSA-11: Verified acquisition of raw and crosstalk-corrected exposures at raft scale, incl. correct metadata¶
- WBS: 02C.07
- Level: 3
- Predecessors: F18F, T&SC-5900-0400
- Successors: DLP-552, LDM-503-06
- Due: 2019-07-29
- Completed: 2020-06-30
Exercise the handoff between the L1 archiving and data backbone endpoint, including a monitoring service that tracks files that have been transfered and received.
A4860: ComCam Systems in Tucson ready for NCSA¶
- WBS: 02C.07.09
- Level: 4
- Successors: LDM-503-09, A5860
- Due: 2019-08-14
- Completed: 2019-08-01
ComCam Test Stand ready for access by NCSA staff.
A4680: June 2019 Travel to Chile - Travel End¶
- WBS: 02C.07.09
- Level: 4
- Successors: LDM-503-09
- Due: 2019-08-16
- Completed: 2019-08-24
End of travel to Chile to install hardware and systems at the Base Data Center.
A4670: June 2019 Travel to Chile - Travel Start¶
- WBS: 02C.07.09
- Level: 4
- Predecessors: A4369.9
- Due: 2019-08-17
- Completed: 2019-08-17
Start of travel to Chile to install hardware and systems at the Base Data Center.
A4750: Summit AA Systems Installed at the Summit¶
- WBS: 02C.07.09
- Level: 4
- Due: 2019-08-29
- Completed: 2019-08-29
Authorization and Authentication systems installed at the Summit.
DM-NCSA-20: ComCam Archiving Service¶
- WBS: 02C.07
- Level: 3
- Predecessors: T&SC-5900-0400
- Successors: LDM-503-11a
- Due: 2019-09-06
- Completed: 2020-06-30
Implment a Service that acquires raw data from a camera at raft scale and sends to NCSA for ingestion into the Data Backbone. This is a preliminary milestone to demonstrate initial capabilities.
A1300: Start Milestone: October 1st, 2019¶
- WBS: 02C.07.05
- Level: Undefined
- Due: 2019-10-01
- Completed: 2019-10-01
Warning
No description available
A6150: Start Milestone: January 1st, 2020¶
- WBS: 02C.07
- Level: 3
- Due: 2020-01-03
- Completed: 2020-01-03
Warning
No description available
DM-NCSA-15: Batch Processing Service for offline spectrograph data processing¶
- WBS: 02C.07
- Level: 3
- Predecessors: DM-DAX-12
- Successors: LDM-503-08
- Due: 2020-11-30
- Completed: 2020-05-29
Demonstrate the ability to process offline Spectrograph data using a science pipeline in the Batch Processing Service. Output(s) will be available in the Data Backbone.
DM-NCSA-22: Information in consolidated database available to QA portal¶
- WBS: 02C.07
- Level: 3
- Predecessors: DM-DAX-12
- Successors: LDM-503-11a
- Due: 2020-11-30
- Completed: 2020-08-31
Scientific and operational data products stored in the consolidated database during ComCam data processing are available for QA assessment of ComCam data through normal analysis access environments.
DM-NCSA-8: Alert Filtering Service receives alert streams¶
- WBS: 02C.07
- Level: 3
- Predecessors: DM-AP-18
- Successors: LDM-503-05, DM-AP-6
- Due: 2020-12-01
- Completion pending
Test instance of feeds to LSST mini broker in online (live stream generated from real-time pipelines) and offline (replaying from files of alert events) modes.
DM-NCSA-21: L1 Offline Processing Service, Raft Scale, ComCam¶
- WBS: 02C.07
- Level: 3
- Successors: LDM-503-11a
- Due: 2020-12-01
- Completion pending
Demonstrated running of processing campaigns in offline mode needed for the ComCam phase of commissioning to debug the instrument. Likely includes calibration, ISR, and other pipelines.
DM-NCSA-23: Operational processes for preparing for & producing a data release defined and tested¶
- WBS: 02C.07
- Level: 3
- Predecessors: F20S
- Successors: DM-NCSA-24, LDM-503-13
- Due: 2020-12-01
- Completion pending
Provide capabilities and processes needed to finalize and prepare a data release after campaign processing is complete. This includes migration of data into release schema, tagging of images files, application of permissions on data, QA work, pushing release products to the DAC, verification of products pushed to the DAC.
DM-NCSA-25: Demonstrate operational coordination with and processing at satellite CC-IN2P3 satellite computing facility¶
- WBS: 02C.07
- Level: 3
- Successors: LDM-503-15
- Due: 2021-11-02
- Completion pending
Provide central job management at NCSA that deploys jobs to CC-IN2P3, optionally with data transfer or using files that are already located in France, and return of outputs to NCSA.
DM-NCSA-14: Data Backbone endpoints in Chile for ingestion and access, distribution over WAN, ingest at NCSA into custodial file sto¶
- WBS: 02C.07
- Level: 3
- Successors: LDM-503-08
- Due: 2021-11-17
- Completion pending
Provide a data Backbone endpoint in Chile, allowing distribution over a wide-area network and ingestion at NCSA.
DM-NCSA-26: Demonstrate full delivery of Data Facility ConOps¶
- WBS: 02C.07
- Level: 3
- Predecessors: S22S
- Successors: LDM-503-16
- Due: 2022-06-10
- Completion pending
Demonstrate readiness of the entire data facility prior to operations. This includes the final operations rehearsal, which will show operational readiness to acquire data and for day to day operations of the LDF with Observatory Operations. This also includes readiness to support LSP and DAC serving data to the broader community.
DM-NCSA-24: Production batch service for data release processing¶
- WBS: 02C.07
- Level: 3
- Predecessors: DM-NCSA-23
- Successors: LDM-503-15
- Due: 2022-07-27
- Completion pending
Provide a Service able to process bulk data according to data release configurations.
02C.08: International Communications and Base Site¶
DM-NET-1: Base - Archive Network Functional 1 Gbps¶
- WBS: 02C.08.02
- Level: 2
- Predecessors: LSST-1440
- Due: 2015-06-11
- Completed: 2015-08-05
Warning
No description available
DLP-42: La Serena to Santiago Path Design Ready¶
- WBS: 02C.08.03
- Level: 3
- Due: 2015-09-28
- Completed: 2015-04-30
Warning
No description available
DMTC-8100-2010: First Data passed on 100G ring without errors - Complete¶
- WBS: 02C.08.03
- Level: 3
- Due: 2015-10-01
- Completed: 2015-10-01
Warning
No description available
DMTC-8000-0760: Technical Implementation plan of fiber connection (primary link) - Complete¶
- WBS: 02C.08.03
- Level: 3
- Successors: DLP-43
- Due: 2015-12-15
- Completed: 2015-12-15
Warning
No description available
DMTC-7400-0815: La Serena-Gatehouse path design Ready¶
- WBS: 02C.08.03
- Level: 3
- Due: 2015-12-15
- Completed: 2015-12-25
Warning
No description available
DLP-43: Fiber Delivery Ready¶
- WBS: 02C.08.03
- Level: 3
- Predecessors: DMTC-8000-0760
- Due: 2015-12-16
- Completed: 2017-02-28
Warning
No description available
DMTC-7400-2010: Gatehouse to La Serena path design Ready - Complete¶
- WBS: 02C.08.03
- Level: 3
- Successors: DLP-41
- Due: 2015-12-16
- Completed: 2015-12-16
Warning
No description available
DLP-41: Mountain - Base Fiber Path Ready¶
- WBS: 02C.08.03
- Level: 3
- Predecessors: DMTC-7400-2010, DMTC-7400-2170
- Due: 2016-01-15
- Completed: 2016-02-29
Warning
No description available
DMTC-7400-2170: Gatehouse to Summit contract signed; Design Ready - Complete¶
- WBS: 02C.08.03
- Level: 3
- Successors: DLP-41
- Due: 2016-01-15
- Completed: 2016-01-15
Warning
No description available
DMTC-7400-2050: Fiber delivery - Complete¶
- WBS: 02C.08.03
- Level: 3
- Due: 2016-03-15
- Completed: 2016-03-31
Warning
No description available
DLP-45: Delivery of “functional Pre-operations Link” (at least 4Gbps), Ready¶
- WBS: 02C.08.03
- Level: 3
- Predecessors: DMTC-8000-0910
- Successors: DMTC-8000-0806
- Due: 2016-04-15
- Completed: 2016-05-02
Warning
No description available
DMTC-8000-0910: Delivery of 4Gbs link from La Serena to Santiago Ready - Complete¶
- WBS: 02C.08.03
- Level: 3
- Successors: DLP-45
- Due: 2016-04-15
- Completed: 2016-06-17
Warning
No description available
DLP-63: Vendor selection Ready¶
- WBS: 02C.08.03
- Level: 3
- Predecessors: DMTC-7400-2290
- Due: 2016-06-01
- Completed: 2016-03-31
Warning
No description available
DMTC-7400-2290: Final Selection of equipment vendor - Complete¶
- WBS: 02C.08.03
- Level: 3
- Successors: DLP-63
- Due: 2016-06-01
- Completed: 2016-10-01
Warning
No description available
DMTC-8100-2050: 100G ring operating at 95.0% availability - Complete¶
- WBS: 02C.08.03
- Level: 3
- Due: 2016-09-28
- Completed: 2016-10-01
Warning
No description available
DMTC-8100-2250: FIU-CIARA Management Contract Delivery #2 Complete¶
- WBS: 02C.08.03
- Level: 3
- Due: 2016-09-30
- Completed: 2016-09-30
Warning
No description available
DMTC-8000-0806: 3T Fiber Installation Certification and Acceptance Test - Complete¶
- WBS: 02C.08.03
- Level: 3
- Predecessors: DLP-45
- Due: 2017-01-02
- Completed: 2017-03-15
Warning
No description available
DLP-37: Summits-Gatehouse Fiber Ready¶
- WBS: 02C.08.03
- Level: 3
- Predecessors: DMTC-7400-2210
- Due: 2017-02-28
- Completed: 2017-05-19
Warning
No description available
DMTC-7400-2210: Fiber delivery by Telefonica - Complete¶
- WBS: 02C.08.03
- Level: 3
- Successors: DLP-37
- Due: 2017-02-28
- Completed: 2017-02-28
Warning
No description available
DMTC-8200-0480: VLAN design finalized Miami-NCSA - Complete¶
- WBS: 02C.08.03
- Level: 3
- Due: 2017-04-24
- Completed: 2017-03-23
Warning
No description available
DMTC-7400-2250: End of commissioning and Acceptance - Complete¶
- WBS: 02C.08.03
- Level: 3
- Successors: DLP-40
- Due: 2017-06-01
- Completed: 2017-06-30
Warning
No description available
DMTC-8100-2474: Agreement with Monet Cable Partner signed Complete¶
- WBS: 02C.08.03
- Level: 3
- Due: 2017-06-30
- Completed: 2017-04-28
Warning
No description available
DMTC-7400-2420: REUNA La Serena - Santiago DWDM equipment - Complete¶
- WBS: 02C.08.03
- Level: 3
- Successors: DMTC-7400-2480, DMTC-7400-2130
- Due: 2017-07-31
- Completed: 2017-08-01
Warning
No description available
DMTC-7400-2090: Report on functional fiber connections, including AURA equipment - Complete¶
- WBS: 02C.08.03
- Level: 3
- Due: 2017-08-18
- Completed: 2017-12-01
Warning
No description available
DMTC-7400-2330: LSST and AURA summit to base DWDM equipment - Complete¶
- WBS: 02C.08.03
- Level: 3
- Successors: DMTC-7400-2130, DLP-40, DLP-65
- Due: 2017-09-29
- Completed: 2017-09-15
Warning
No description available
DMTC-8100-2290: FIU-CIARA Management Contract Delivery #3 Complete¶
- WBS: 02C.08.03
- Level: 3
- Due: 2017-09-29
- Completed: 2017-09-01
Warning
No description available
DMTC-7400-2480: AURA DWDM equipment in operation - Complete¶
- WBS: 02C.08.03
- Level: 3
- Predecessors: DMTC-7400-2420
- Successors: DMTC-8000-0818, DMTC-7400-2510
- Due: 2017-10-30
- Completed: 2017-11-01
Warning
No description available
DMTC-8000-0818: Acceptance Test with Equipment Installed - Complete¶
- WBS: 02C.08.03
- Level: 3
- Predecessors: DMTC-7400-2480
- Due: 2017-11-30
- Completed: 2017-12-01
Warning
No description available
DMTC-7400-2510: REUNA La Serena - Santiago Optical Channel in operation - Complete¶
- WBS: 02C.08.03
- Level: 3
- Predecessors: DMTC-7400-2480
- Due: 2017-11-30
- Completed: 2017-11-01
Warning
No description available
DMTC-7400-2130: End of commissioning. Acceptance of fiber connection - Complete¶
- WBS: 02C.08.03
- Level: 3
- Predecessors: DMTC-7400-2420, DMTC-7400-2330
- Due: 2017-11-30
- Completed: 2017-12-01
Warning
No description available
DLP-44: La Serena to Santiago with test traffic AURA DWDM LSST Fiber¶
- WBS: 02C.08.03
- Level: 3
- Predecessors: DMTC-8000-0826
- Due: 2018-03-02
- Completed: 2017-12-31
Warning
No description available
DMTC-8000-0826: Intermediate traffic testing and report - Complete¶
- WBS: 02C.08.03
- Level: 3
- Successors: DLP-44
- Due: 2018-03-02
- Completed: 2018-03-02
Warning
No description available
DLP-61: La Serena – Santiago link Ready¶
- WBS: 02C.08.03
- Level: 3
- Predecessors: S17F
- Successors: DMTC-8000-0836
- Due: 2018-03-14
- Completed: 2018-01-12
Warning
No description available
DLP-40: Summits-Gatehouse Initial Capability Ready¶
- WBS: 02C.08.03
- Level: 3
- Predecessors: DMTC-7400-2250, DMTC-7400-2330
- Due: 2018-03-14
- Completed: 2017-12-22
Warning
No description available
DLP-65: Mountain - Base LSST and AURA DWM End Node Installation and Test Ready¶
- WBS: 02C.08.03
- Level: 3
- Predecessors: DMTC-7400-2330
- Due: 2018-03-14
- Completed: 2018-03-31
Warning
No description available
DM-NET-2: Mountain - Base Network Functional 2 x 100 Gbps¶
- WBS: 02C.08.01
- Level: 1
- Predecessors: DLP-559
- Successors: LDM-503-08, COMC-0620-2050
- Due: 2018-03-27
- Completed: 2018-04-02
Warning
No description available
DMTC-8100-2490: First light test report - Complete Contract¶
- WBS: 02C.08.03
- Level: 3
- Due: 2018-04-02
- Completed: 2018-06-01
Warning
No description available
DMTC-8000-0836: La Serena to Santiago with live traffic and uptime over LSST Lambda Ready - Complete¶
- WBS: 02C.08.03
- Level: 3
- Predecessors: DLP-61
- Due: 2018-05-11
- Completed: 2019-07-23
Warning
No description available
DMTC-8100-2090: 100G ring operating at 97.0% availability - Complete¶
- WBS: 02C.08.03
- Level: 3
- Successors: DLP-36
- Due: 2018-06-29
- Completed: 2018-06-29
Warning
No description available
DMTC-8200-0510: ESNet Request - Complete¶
Warning
No description available
DM-NET-3: Initial Network Ready (Summit)¶
- WBS: 02C.08.03
- Level: 2
- Predecessors: T&SC-2600-1545
- Successors: LDM-503-08
- Due: 2018-09-28
- Completed: 2018-03-05
Warning
No description available
DM-NET-6: Summit LAN installed¶
- WBS: 02C.08.00
- Level: 3
- Predecessors: T&SC-2600-1545
- Successors: LDM-503-08
- Due: 2018-09-28
- Completed: 2018-04-02
Warning
No description available
DMTC-8100-2330: FIU-CIARA Management Contract Delivery #4 Complete¶
- WBS: 02C.08.03
- Level: 3
- Due: 2018-10-01
- Completed: 2018-10-31
Warning
No description available
DMTC-8100-2530: Data passing test report - Complete¶
- WBS: 02C.08.03
- Level: 3
- Successors: DLP-33
- Due: 2018-10-26
- Completed: 2019-05-31
Contract Deliverable Report #4 Spectrum Complete. Test of first data passing over Santiago - Boca Raton Specturm link.
IT-716-M: Base Center Beneficial Occupancy¶
- WBS: 02C.08.01
- Level: Undefined
- Predecessors: T&SC-0400-1600
- Due: 2018-11-26
- Completed: 2019-03-18
Warning
No description available
IT-718-M: Base Center Full Occupancy¶
- WBS: 02C.08.01
- Level: Undefined
- Due: 2019-02-12
- Completed: 2019-06-30
Externally linked to TS milestone for full occupancy of Base Data Center, including all construction, utilities, access and dust control.
DMTC-8000-0870: Report on functional fiber, including uptime, 1st year functional milestone - Complete¶
- WBS: 02C.08.03
- Level: 3
- Due: 2019-03-22
- Completed: 2019-07-23
Contract Deliverable Report #8 Report on functional fiber, including uptime, 1st year functional milestone - Complete. Covers first year of operational service of La Serena - Santiago primary fiber, including availability and outage information.
DLP-36: Santiago - Miami Early Integration Ready¶
- WBS: 02C.08.03
- Level: 3
- Predecessors: DMTC-8100-2090, DMTC-8100-2112
- Successors: DLP-468
- Due: 2019-04-22
- Completed: 2018-06-01
Warning
No description available
DMTC-8100-2112: Miami - Boca Raton path diverse fiber - Complete¶
- WBS: 02C.08.03
- Level: 3
- Successors: DLP-36
- Due: 2019-04-22
- Completed: 2019-02-01
Warning
No description available
DMTC-8100-2130: 100G ring operating at 98.0% availability - Complete¶
- WBS: 02C.08.03
- Level: 3
- Due: 2019-05-08
- Completed: 2019-02-13
Warning
No description available
IT-716-M2: Furniture installed in Offices, purchased cabling received¶
- WBS: 02C.08.01
- Level: Undefined
- Due: 2019-05-31
- Completed: 2019-10-31
Externally linked to TS milestone for installation of furniture of Base Office Building and Base Data Center. All cabling to connect offices to Base LAN has been received.
DMTC-8000-0950: Technical Implementation Plan for 40Gbps diverse path - Complete¶
- WBS: 02C.08.03
- Level: 3
- Due: 2019-06-05
- Completed: 2019-03-25
Contract Deliverable Report #10 Technical Implementation Plan for 40Gbps diverse path - Complete. Covers the fiber and equipment, ownership/service levels for La Serena - Santiago secondary path.
DM-NET-4: Base LAN installed¶
- WBS: 02C.08.03
- Level: 2
- Successors: LDM-503-11
- Due: 2019-07-15
- Completed: 2020-01-31
Installed the Base LAN equipment in the Base Date Center and Base Office Building technical closets, and cabling connecting them for the Base Campus and Control Networks. Tested with data volumes and access points equivalent to operational staffing and control servers for ATS observing. (Level 2 equivalent of Level 3 milestone IT-725-M).
DMTC-8100-2370: FIU-CIARA Management Contract Delivery #5 Complete¶
- WBS: 02C.08.03
- Level: 3
- Due: 2019-09-30
- Completed: 2019-12-31
Level of effort management task, annual report delivered, covering all activities, meetings, conferences/workshops, circuits, tools, tests, staffing, budget/expenditures.
DLP-70: Miami - Chicago Early Integration Ready¶
- WBS: 02C.08.03
- Level: 3
- Predecessors: DMTC-8200-0510
- Due: 2019-10-01
- Completed: 2019-11-01
Miami - Atlanta, and ESNet Atlanta - Chicago 2 x 20 Gbps path diverse circuits available and tested at capacity.
DLP-69: Boca Raton - Chicago Early Integration Ready¶
- WBS: 02C.08.03
- Level: 3
- Predecessors: DMTC-8200-0510
- Due: 2019-10-01
- Completed: 2019-11-14
Boca Raton - Atlanta and ESNet Atlanta - Chicago 2 x 20 Gbps path diverse circuits available and tested at capacity.
DMTC-8200-0600: ESNet Implementation Phase 1- Complete¶
ESNet Atlanta - Chicago 2 x 20 Gbps path diverse circuits available and tested at capacity.
DMTC-8100-2170: 100G ring operating at 99.0% availability - Complete¶
- WBS: 02C.08.03
- Level: 3
- Due: 2020-07-02
- Completed: 2020-02-19
Contract Deliverable Report #6 100G managed ring Contract Delivery #6 Complete. Covers availability and outages.
DLP-33: Santiago - Boca Raton Full Integration Ready¶
- WBS: 02C.08.03
- Level: 3
- Predecessors: DMTC-8100-2530, S18F
- Successors: LSST-1580
- Due: 2020-09-15
- Completed: 2019-08-31
Spectrum link operational at 100 Gbps from Santiago - Boca Raon, including terrestrial segment from Santiago - Sao Paolo, and Monet submarine cable from Sao Paolo - Boca Raton.
IT-725-M: Base Data Center Network Complete¶
- WBS: 02C.08.01
- Level: Undefined
- Successors: LDM-503-10
- Due: 2020-12-01
- Completion pending
Installed the Base LAN equipment in the Base Data Center and Base Office Building technical closets, and cabling connecting them for the Base Campus and Control Networks. Tested with data volumes and access points equivalent to operational staffing and control servers for ATS observing. (Level 3 equivalent of Level 2 milestone DM-NET-4).
DLP-46: Full Capacity over Diverse path Ready¶
- WBS: 02C.08.03
- Level: 3
- Predecessors: DMTC-8000-0990, S19F
- Due: 2020-12-01
- Completion pending
Both primary (100 Gbps) and secondary (40 - 100 Gbps) circuits from La Serena - Santiago are operational and tested with loads to full capacity.
DMTC-8000-0990: Full capacity La Serena to Santiago over Primary link AND Secondary link - Complete¶
- WBS: 02C.08.03
- Level: 3
- Successors: DLP-46
- Due: 2020-12-01
- Completion pending
Contract Deliverable Report #11 Full capacity La Serena to Santiago over Primary link AND Secondary link - Complete. Covers the results of testing of the La Serena - Santiago primary and secondary paths.
DMTC-8100-2410: FIU-CIARA Management Contract Delivery #6 Complete¶
- WBS: 02C.08.03
- Level: 3
- Due: 2021-02-10
- Completion pending
Level of effort management task, annual report delivered, covering all activities, meetings, conferences/workshops, circuits, tools, tests, staffing, budget/expenditures.
DLP-465: Install networking for normal Base Center operations for full-camera scale¶
- WBS: 02C.08.01
- Level: 3
- Predecessors: F20F
- Successors: LSST-1580, CAMM8350
- Due: 2021-06-04
- Completed: 2020-11-30
Installed the Base LAN equipment in the Base Data Center and Base Office Building technical closets, and cabling connecting them for the Base Campus and Control Networks. Tested with data volumes and access points equivalent to operational staffing and control servers for full camera observing.
DLP-468: Provide networking for formal Chilean DAC production at full-camera scale¶
- WBS: 02C.08.02
- Level: 3
- Predecessors: DLP-36, F20F
- Successors: LDM-503-11
- Due: 2021-06-04
- Completed: 2020-11-30
Installed the Base LAN equipment in the Chilean DAC. Tested with data volumes and access points equivalent to anticipated DAC user workload contemporaneous with full camera observing.
DLP-467: Install networking for full-camera-scale Chilean DAC serving on order 80 people¶
- WBS: 02C.08.02
- Level: 3
- Predecessors: F20F
- Successors: LDM-503-11
- Due: 2021-06-04
- Completed: 2020-11-30
Installed the Base LAN equipment in the Chilean DAC. Tested with data volumes and access points equivalent to anticipated DAC user workload contemporaneous with commissioning camera observing.
DMTC-8100-2210: 100G ring operating at 99.99% availability - Complete¶
- WBS: 02C.08.03
- Level: 3
- Due: 2021-06-30
- Completion pending
Contract Deliverable Report #7 100G managed ring Contract Delivery #7 Complete. Covers availability and outages.
DLP-877: Miami - Chicago Full Integration Ready¶
- WBS: 02C.08.03
- Level: 3
- Predecessors: DMTC-8200-0600, S19F
- Due: 2021-06-30
- Completion pending
Miami - Atlanta and ESNet Atlanta - Chicago 2 x 100 Gbps path diverse circuits available and tested at capacity.
DLP-876: Boca Raton - Chicago Full Integration Ready¶
- WBS: 02C.08.03
- Level: 3
- Predecessors: DMTC-8200-0600, S19F
- Due: 2021-06-30
- Completion pending
Boca Raton - Atlanta and ESNet Atlanta - Chicago 2 x 100 Gbps path diverse circuits available and tested at capacity.
DMTC-8200-6020: ESNet Implementation Phase 2- Complete¶
- WBS: 02C.08.03
- Level: 3
- Successors: LSST-1580
- Due: 2021-07-01
- Completion pending
ESNet Atlanta - Chicago 2 x 100 Gbps path diverse circuits available and tested at capacity.
DM-NET-5: Base - Archive Network Functional 100 Gbps¶
- WBS: 02C.08
- Level: 2
- Predecessors: DLP-464, COMC-0021
- Successors: CAMM8330, CAMM8340, COMC-0620-2240
- Due: 2021-07-09
- Completion pending
All segments of the Base - Archive Network, including La - Serena - Santiago - Sao Paolo - Miami/Boca Raton - Chicago - Champaign are operationally available at 100 Gbps line rate (effective rate is typically lower, ~ 80%).
DLP-464: Install networking for normal Base Center operations for ComCam scale¶
- WBS: 02C.08.01
- Level: 3
- Predecessors: F18F
- Successors: CAMM8340, DM-NET-5, COMC-060200-20790
- Due: 2021-07-09
- Completed: 2020-11-30
Installed the Base LAN equipment in the Base Data Center and Base Office Building technical closets, and cabling connecting them for the Base Campus and Control Networks. Tested with data volumes and access points equivalent to operational staffing and control servers for commissioning camera observing.
DLP-466: Install networking for ComCam-scale Chilean DAC serving on order 20 people¶
- WBS: 02C.08.02
- Level: 3
- Predecessors: F18F
- Successors: LSST-1580, CAMM8330, CAMM8340, COMC-060200-20790
- Due: 2021-07-09
- Completed: 2020-11-30
Installed the Base LAN equipment in the Chilean DAC. Tested with data volumes and access points equivalent to anticipated DAC user workload contemporaneous with ATS observing.
DMTC-8100-2450: FIU-CIARA Management Contract Delivery #7 Complete¶
- WBS: 02C.08.03
- Level: 3
- Due: 2021-09-30
- Completion pending
Level of effort management task, annual report delivered, covering all activities, meetings, conferences/workshops, circuits, tools, tests, staffing, budget/expenditures.
02C.09: System Level Testing & Science Validation (Obsolete)¶
02C.10: Science Quality and Reliability Engineering¶
DLP-340: Operating system testing for public stack releases increased¶
Warning
No description available
DLP-334: SQuaRE release improved or changed CI system¶
- WBS: 02C.10.02
- Level: 3
- Successors: DLP-337
- Due: 2015-08-31
- Completed: 2016-04-08
Warning
No description available
DLP-342: Publish updated introductory software guide to developing with the stack¶
- WBS: 02C.10.02
- Level: 3
- Predecessors: DLP-340
- Due: 2015-12-29
- Completed: 2016-04-08
Warning
No description available
DLP-341: Deploy stack user support and discussion forum¶
- WBS: 02C.10.02
- Level: 3
- Predecessors: DLP-340
- Successors: DLP-337
- Due: 2015-12-29
- Completed: 2016-04-08
Warning
No description available
DLP-337: Release new stack documentation infrastructure¶
Warning
No description available
DLP-345: Prototype metrics collection system deployed¶
- WBS: 02C.10.02
- Level: 3
- Due: 2016-02-29
- Completed: 2016-05-31
Warning
No description available
DLP-351: Intermediate Performance Metrics routinelly calculated and published¶
- WBS: 02C.10.02
- Level: 3
- Due: 2016-02-29
- Completed: 2016-05-31
Warning
No description available
DLP-346: SQuaSH Prototype using existing architectural components deployed¶
- WBS: 02C.10.02
- Level: 3
- Due: 2016-08-31
- Completed: 2017-07-25
Warning
No description available
DM-SQRE-1: Project internal Jupyter notebook service¶
- WBS: 02C.10.02
- Level: 3
- Successors: LDM-503-01, DM-SQRE-2
- Due: 2017-08-31
- Completed: 2017-11-01
Warning
No description available
DLP-344: Release SQuaSH-in-a-box automated deployment platform¶
- WBS: 02C.10.02
- Level: 3
- Predecessors: F17F
- Due: 2017-11-30
- Completed: 2017-11-01
Warning
No description available
DLP-352: Metrics of Interest integrated in running stack or post-tests¶
Warning
No description available
DM-SQRE-2: Notebook service capabilities are suitable for the commissioning team to develop notebooks for its needs¶
- WBS: 02C.10.02
- Level: 3
- Predecessors: DM-SQRE-1
- Successors: LDM-503-09, DM-SQRE-3
- Due: 2018-11-30
- Completed: 2019-11-29
Members of the integration and commissioning team are able to develop notebooks in nublado that are capable of the interactive data exploration that is suitable to their needs to support ComCam commissioning. Data is available via a Butler to a mounted filesystem. They are able to work effectively, though in some cases their user experience can be improved. They are primarily trained in person by bootcamps and may require extensive support via Slack. The service may be intermittently unavailable due to engineering work.
DM-SQRE-3: Notebook service stable for commissioning and other internal project users¶
- WBS: 02C.10.02
- Level: 3
- Predecessors: DM-SQRE-2
- Successors: LDM-503-12, DM-SQRE-4
- Due: 2020-02-27
- Completed: 2020-01-30
Members of the integration and commissioning team as well as science pipelines developers use nublado to support their interactive data exploration needs relating to ComCam commissioning. They are able to work effectively though in some cases their user experience can be improved. Access to EFD data is easily available from notebooks. Data is available via Butler to a mounted filesystem. There is a curated library of notebooks modeling common tasks and a way to automatically verify that they are in working condition. Users can refer to documentation for answers to common problems. The service is stable and interruptions to the service are primarily notified well in advance and co-ordinated with the commissioning team to minimise disruption to the extent that the underlying infratsructure permits it.
DM-SQRE-6: IVOA Server-side Operations for Data Access API¶
- WBS: 02C.10.02
- Level: 3
- Predecessors: F20F
- Successors: LSST-1580, DM-SQRE-7
- Due: 2021-06-02
- Completion pending
Warning
No description available
DM-SQRE-7: IVOA-compliant image metadata services¶
- WBS: 02C.10.02
- Level: 3
- Predecessors: F20F, DM-SQRE-6
- Successors: LSST-1580
- Due: 2021-06-02
- Completion pending
Warning
No description available
DM-SQRE-4: Notebook service ready for verification & validation¶
- WBS: 02C.10.02
- Level: 3
- Predecessors: DM-SQRE-3, COMC-060200-10100
- Successors: LDM-503-14
- Due: 2022-03-14
- Completion pending
Science pipeline developers and members of the verification and validation science team use nublado to support their interactive data exploration needs relating to comcam commissioning. They are able to work effectively though in some cases their user experience can be improved. As well as access to EFD, catalogue and pixel data, they have access to any available APIs to the workflow/batch system for non-trivial data processing. There are curated libraries of continuously integrated notebooks modeling common tasks and they is a reasonable workflow to allow Github-based collaboration on those notebooks. Users can refer to documentation for how to get started and for answers to common problems. The service is stable with minimal interruptions, but may not always scale well to large number of users.
DM-SQRE-5: Notebook service ready for general science users¶
- WBS: 02C.10.02
- Level: 3
- Predecessors: LSST-1560
- Successors: LSST-1580, DM14
- Due: 2023-03-22
- Completion pending
Members of the science collaborations or other non-project staff with access to data use nublado to support their interactive scientific data exploration. They are able to share data with each other using LSP sharing mechanisms and can access data without a direct filesystem mount (eg VO services, remote Butler etc). The service scales well to large number of users provided the infrastructure is sized for them. Users can primarily rely on documentation for support, and use a helpdesk system for questions. There is robust functionality for performing large distributed catalog operations and for visually exploring LSSTCam sized images.
Bibliography¶
[1] | (1, 2) [LDM-533]. Eric C. Bellm. Level 1 System Software Test Specification. 2017. URL, https://ls.st/LDM-533. |
[2] | [DMTR-182]. M. Butler. Ldm-503-10b: large scale ccob data access test plan and report. 2019. Draft version. URL: http://dmtr-182.lsst.io |
[3] | [DMTR-181]. M. Butler. Ldm-503-10: daq validation test plan and report. 2020. URL, https://ls.st/DMTR-181. |
[4] | [DMTR-171]. M. Butler. Ldm-503-6: comcam interface verification readiness test plan and report. 2020. URL, https://ls.st/DMTR-171. |
[5] | [DMTR-121]. Michelle Butler. Ldm-503-8 (spectrograph data acquisition) test plan and report. 2019. URL: http://dmtr-121.lsst.io |
[6] | [DMTR-102]. Michelle Butler. Ldm-503-8b (small scale ccob data access) test plan and report. 2019. URL: http://dmtr-102.lsst.io |
[7] | (1, 2) [LDM-538]. Michelle Butler, Jim Parsons, and Michelle Gower. Raw Image Archiving Service Test Specification. 2018. URL, https://ls.st/LDM-538. |
[8] | [DMTR-161]. G. Dubois-Felsmann. Ldm-503-10a: lsp with authentication and tap test plan and report. 2020. URL, https://ls.st/DMTR-161. |
[9] | [LDM-540]. Gregory Dubois-Felsmann. LSST Science Platform Test Specification. 2018. URL, https://ls.st/LDM-540. |
[10] | [LDM-554]. Gregory Dubois-Felsmann, David Ciardi, Fritz Mueller, and Frossie Economou. Science Platform Requirements. 2018. URL, https://ls.st/LDM-554. |
[11] | [LDM-542]. Gregory Dubois-Felsmann, Kian-Tat Lim, Xiuqin Wu, Frossie Economou, Fritz Mueller, Brian Van Klaveren, and Kenny Lo. LSST Science Platform Design. 2017. URL, https://ls.st/LDM-542. |
[12] | (1, 2) [LDM-643]. M. Johnson and R.A. Gruendl. Proposed DM OPS Rehearsals. 2019. URL, https://ls.st/LDM-643. |
[13] | [LSE-319]. M. Jurić, D. Ciardi, and G.P. Dubois-Felsmann. LSST Science Platform Vision Document. 2017. URL, https://ls.st/LSE-319. |
[14] | [LSE-163]. Mario Jurić and others. LSST Data Products Definition Document. 2017. URL, https://ls.st/LSE-163. |
[15] | [LSE-400]. K-T Lim. Header Service Interface. 2019. URL: https://lse-400.lsst.io |
[16] | (1, 2) [LDM-148]. K.-T. Lim, J. Bosch, G. Dubois-Felsmann, T. Jenness, J. Kantor, W. O’Mullane, D. Petravick, and The DM Leadership Team. Data Management System Design. 2018. URL, https://ls.st/LDM-148. |
[17] | (1, 2, 3, 4, 5) [LDM-564]. William O’Mullane, Frossie Economou, Tim Jenness, and Andrew Loftus. Data Management Software Releases for Verification/Integration. 2018. URL, https://ls.st/LDM-564. |
[18] | [DMTR-191]. J. Swinbank. Ldm-503-11b: science pipelines fall 2019 release test plan and report. 2019. Draft version. URL: http://dmtr-191.lsst.io |
[19] | [DMTR-112]. J.D. Swinbank. LDM-503-07 (Camera data processing) Test Plan and Report. 2018. URL, https://ls.st/DMTR-112. |
[20] | [DMTR-111]. J.D. Swinbank. LDM-503-09a (Science pipelines fall 2018 release) Test Plan and Report. 2018. URL, https://ls.st/DMTR-111. |
[21] | [LDM-534]. John D. Swinbank. Level 2 System Software Test Specification. 2017. URL, https://ls.st/LDM-534. |
[22] | (1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25, 26, 27, 28, 29, 30, 31, 32) [LDM-151]. John D. Swinbank and others. Data Management Science Pipelines Design. 2017. URL, https://ls.st/LDM-151. |